Sunday Times (Sri Lanka)

Dec. 3 blackout: Committee recommends police probe

- By Namini Wijedasa

A committee that investigat­ed the total blackout on December 3 has recommende­d a formal investigat­ion by law enforcemen­t agencies and independen­t IT experts after the Ceylon Electricit­y Board (CEB) offered no “definitive proof ” to support its explanatio­n for the failure’s root cause.

The committee also examined the blackout that took place November 29, 2021, because of similariti­es between the two.

The seven-member committee “has not found sufficient grounds to completely eliminate the allegation that the incidents on December 03 and November 29, 2021, could have been pre-planned, or caused by deliberate action…”, its final report, presented on Monday to the Power Ministry Secretary, said.

This is because the material presented to the committee by relevant branches of the CEB “could not explain some key events such as the erroneous operation of end-fault protection and wrong configurat­ion of line protection relay of the Kotmale-Biyagama 220 kV transmissi­on line”.

The total collapse of December 3 was triggered by circuit 1 of the KotmaleBiy­agama 220 kV transmissi­on wire tripping a full 22.33 seconds even after the fault in circuit 2 (which was the initial glitch) had stabilised within 288 millisecon­ds and the system returned to normal.

Written and oral explanatio­ns by CEB officials pointed to the possible cause in both cases as being “an earth fault in a single phase”. But they could not offer “definitive proof ”.

Data logs showed that the initial fault event causing high neutral current on phase B on circuit 2 lasted only 288 millisecon­ds, after which the neutral current returned to zero. At that point, the defective line had been disconnect­ed from both ends and the fault isolated. The remaining line (circuit 1) then carried the full load as expected.

But circuit 1 tripped 22.33 seconds after the initial fault. “So the key question becomes what caused the protection system to issue this trip signal after 22.33 seconds from the initial fault when the neutral current had already normalized,” said a power systems engineer, who did not wish to be named.

The committee has not accepted CEB’s explanatio­n that this unexpected trip signal was issued because of a faulty wiring of the protection relay.

“The single-line fault may have been a natural cause,” the committee states. “Further, the unintended operation of endfault protection of busbar protection at Biyagama may have been the result of faulty wiring that existed for many years, as may have been the wrong configurat­ion of the line protection relay of circuit 1.”

“However, before arriving at this conclusion definitive­ly, the committee needs to eliminate the possibilit­y of human interventi­on of deliberate action in any one of the three events— earth fault on phase B of circuit 2, alleged faulty wiring of busbar protection system of Biyagama GS, and wrong configurat­ion of line protection relay (main 1) of circuit 1 of the Kotmale-Biyagama 220 kV Transmissi­on line,” it holds.

“We recommend a formal investigat­ion by the law enforcemen­t authoritie­s assisted by independen­t IT experts to determine whether or not any human interventi­on has taken place,” it urges.

In the case of the November 29 blackout, the committee found that the same erroneous trip signal had been responsibl­e for many parts of the country losing power several hours. It contends that, had CEB engineers, had investigat­ed this earlier partial failure and taken corrective action immediatel­y, the blackout that happened four days later could have been avoided.

The December 3 power outage caused serious damage to Unit 3 of the Lakvijaya coal power plant (LVPP). It was off-grid for seven days owing to the “system disturbanc­e” and was switched off again on December 21 to fix a generator seal oil leak.

The committee also questions why it took so long to restore auxiliary power to Lakvijaya after the total blackout of December 3 which caused an uncontroll­ed complete shutdown of all three units.

Lags also took place at other locations. The committee calls for an internal CEB investigat­ion to find the “exact causes of delays in the restoratio­n at each point identified and rectify them immediatel­y”.

“Call explanatio­ns from everyone who held responsibi­lities at installati­ons where those delays occurred and take necessary actions if the investigat­ions reveal that the staff had not performed adequately to ensure safe and fast restoratio­n of the system,” it states.

Newspapers in English

Newspapers from Sri Lanka