Sunday Times (Sri Lanka)

The hurry to award the Central Expressway Project hara-kiri for Lanka’s economy

- By Dr Amal S Kumarage (The writer is a Senior Professor at the Moratuwa University's Department of Transport & Logistics)

Having studied road constructi­on costs in ninety-nine low and middle-income countries, the World Bank has derived an average constructi­on cost for a nonurban four-lane expressway of $2.8 million/km, with a maximum of $7.8 million/ km. The CEP-3 constructi­on cost alone ranges more than ten times this average

Namini Wijedasa writing in the Sunday Times of March 27 under the headline ' Highway Ministry Speeding ahead with controvers­ial bid', raises the alarm that another controvers­ial expressway contract may be awarded.

The proposed 19.6 km Rambukkana- Galagedera section of the Central Expressway Project ( CEP) appears to be yet another faux-pas, which is in no way beneficial to the country and its economy and will further impede Sri Lanka's economic recovery.

The hurry and the secrecy in which the authoritie­s are proceeding can only be interprete­d to benefit certain individual­s. The question is: Should the cost of investment­s that only benefit certain individual­s continue to be borne by the people?

Continuing legacy of a decade of reckless expressway spending

Expressway building began with a concept the RDA developed in the early 1990s. Financing difficulti­es delayed constructi­on till 2001, when the ADB and JICA jointly financed the E01 to Matara ( Godagama). The contract was initially awarded on competitiv­e bidding at $6 million/km, the final cost being $ 7.1 million/ km. The E03, the Katunayake Expressway, was the first to be awarded in 2009 on a negotiated basis. The cost increased to $ 14.9 million/ km, clearly revealing the large margins that could be earned from expressway constructi­on when they are negotiated without competitiv­e tendering. The E02 Outer Circular Highway ( OCH), financed by JICA, fell victim next. The OCH-2 was awarded to a Japanese company after the Cabinet decided to negotiate, resulting in spending $38.7 million/km, estimated to have been 2-3 times the cost if competitiv­e bids had been called.

After 2012, expressway­s became a lucrative business for those in power and their cronies. No multi-lateral financing agency -- such as the ADB, WB, or JICA -- which funds expressway­s globally at low interest/concession­ary rates, was interested in financing poorly planned and exorbitant­ly priced expressway­s. The Mahinda Rajapaksa Gover nment entertaine­d non- competitiv­e bids for the OCH- 3 from Kadawatha to Kerawelapi­tiya. Meanwhile, the alignment of Section 1 of the Central Expressway ( CEP) was shifted by the Rajapaksa government for political reasons, resulting in a costly new interchang­e at Enderamull­a. This prompted my first article in the Sunday Times on December 21, 2014, exposing corruption.

The Yahapalana Government started well by reversing the interchang­e from Enderamull­a to Kadawatha as originally planned and requested a 25.9% reduction from the contractor, the Metallurgi­cal Corporatio­n of China Ltd. (MCC). However, only 15% materialis­ed with Section 1 of the CEP awarded to the same company without any competitiv­e bid as part of the negotiated deal. This project has, in recent times, been subjected to huge variations due to political interventi­ons and is likely to cost at least $ 21.2 million/ km when completed.

The Yahapalana government also awarded the extension of the Southern Highway from Matara to Mattala/Hambantota at the cost of $ 19.8 million/ km (2.8 times the E01 to Matara) in 2015. The return to non-competitiv­e awards led to my second article in the Sunday Times on November 20, 2016, calling the Yahapalana government not to continue what its predecesso­r had done. But that too fell on deaf ears.

The CEP- 2 from Mirigama to Kurunegala was awarded to four consortia of local contractor­s at around the cost as section 1. But, the poor planning, design and project management resulted in the initial cost of Rs 137.4 bn increasing to at least Rs 170 bn, at $27.7 million/km.

The cur rent Gotabaya Rajapaksa government started working on a 12.9 km section of CEP- 3 from Potuhera to Rambukkana in 2020 by awarding contracts to local companies that worked on CEP- 2. But neither a cost estimate nor a proposal is available publicly.

Please see the table which shows that expressway­s have cost $ 7.3 billion to the national economy. This does not include the financing cost that ranges from 0.5 - 1% p. a. for the ADB, JICA borrowings, and 2-3% p.a. for others. Thus, a conservati­ve estimate, including total financing cost, would exceed $9 billion.

A study of national budgets of the last six years reveals that 44% of all the foreign borrowings have been raised for roads and expressway­s. That the country has sunk deeper into economic hardship and financial bankruptcy shows that these highways, instead of making the economy more robust and more productive, have contribute­d to its downfall.

Moreover, even with this severe burden on the national economy, Sri Lanka will have only 389 km of expressway out of a road network of 120,000 km. The expressway­s will carry less than 2% of all vehicle km.

The hidden financing cost in cep-3 bid

The Potuhera-Galagedera section of CEP-3 runs through hilly terrain, and a higher cost per km is inevitable. The RDA's engineerin­g cost of Rs 163 bn ($41.8 million/ km) was calculated in 2021. Though laudable and a departure from unsolicite­d proposals, this project's call for competitiv­e bids has now run into several transparen­cy issues. Unlike all other expressway projects, this bid is to build and maintain the facility for 15 years.

The MCC, involved in expressway constructi­on in Sri Lanka since 2009 and having profited from several unsolicite­d awards, recently complained to the President that a bid of $1872 million payable in 30 semi- annual instalment­s of $62.4 million from a local company whom they have identified as LIDC, was being considered even though the MCC cost proposal was only $1070 million. It includes the cost of constructi­on, operationa­l and maintenanc­e (O&M) for 15 years, and the cost of financing. Negotiatio­ns are underway where the bid value is being reduced to match the Engineer's estimate according to RDA documents. The original bid condition was for the semi- annual annuity to be paid in Rupees ( LKR) converted by the USD exchange rate prevailing at payment. The revised bid price is now to be given in LKR. The bidder is to be compensate­d for any depreciati­on of the LKR. Though this vague statement appears beneficial for the current foreign exchange crisis, it will neverthele­ss not reduce the cost of the project, which will remain at its dollar value.

However, the primary concern of the project is its financing cost. Based on the RDA Engineer's Estimate, the cost of civil works and the O&M cost for 15 years would be around $ 820 million. It leaves a margin of $ 250 million or ( 30%) as the financing cost for the MCC bid and $1052 million (128%) for the LIDC bid. If so, a quick calculatio­n establishe­s that the cost of financing the MCC bid is around 3-4% p.a. In comparison, that of the LIDC is over 15% p. a., with both payments in the LKR equivalent to the prevailing dollar rate.

The move between 2009 and 2012 to obtain unsolicite­d proposals doubled and tripled expressway costs. The financing arrangemen­t for the CEP- 3 appears to be a new strategy that will further raise this to global highs. Having studied road constructi­on costs in ninety- nine low and middle- income countries, the World Bank has derived an average constructi­on cost for a non- urban four- lane expressway of $ 2.8 million/ km, with a maximum of $ 7.8 million/ km. The CEP- 3 constructi­on cost alone ranges more than ten times this average. The World Bank report reveals that when costs are higher, they usually relate to the Transparen­cy Index, which measures corruption levels in a country.

RDA's studies show that the CEP- 3 will be a significan­t economic loss

The feasibilit­y studies of the project (available on the project website) prove this so that even a court order should be possible to stop this wanton destructio­n of our economy at this precarious time.

Let me explain why I can say this boldly. There has been just one feasibilit­y study carried out in 2016 for the entire CEP from Kadawatha to Dambulla, linking to Galagedera, totalling 170 km. It was estimated at Rs 476.5 billion, equivalent to $3.33 billion. The study has determined an internal economic rate of return (EIRR) of 9.0% for constructi­ng this highway in four stages with a Net Present Value (NPV) of Rs 200.1 billion. It indicates the project to be a relatively poor economic investment.

The RDA's feasibilit­y study reveals that while the CEP- 1 ( Kadawatha- Mirigama) has a higher return EIRR of 14.9%, the returns (NPV) diminish as it progresses. If the other sections are assessed individual­ly, to perceive their viability, their EIRR is likely to fall below 9.0%, clearly establishi­ng a prima- facie case that some of these sections are premature to build. With the current cost of the CEP at $28.1 million per km, ( 40% higher than the feasibilit­y study), based on its sensitivit­y analysis, the EIRR for the entire CEP drops to 7.3%, well below-accepted levels.

The Environmen­tal Study for CEP’s Potuhera-Galagedera section, presently under negotiatio­ns, reveals the EIRR of this section to be only 8.4%, with an NPV of Rs. 127.1 billion. Moreover, applying the proposed cost, which is an increase of 72% over the cost assumed in the feasibilit­y study, makes the NPV negative, indicating that the proposed expressway will be a net economic loss to the country. This means the country will incur a net loss by proceeding with this project, even at the Engineer's Estimate and without financing costs. However, the related consultant­s, contractor­s, and individual­s will line their pockets with profits. Thus, the people should call for an immediate halt to this project. Instead of continuing with this project, appropriat­e alternativ­es should be sought, focussing on the urgent need for short-term economic revival.

The alternativ­es

Studies show that spending under 50% of the cost of the CEP-3 on railway improvemen­ts will reduce express railway travel time to Kandy from 150 minutes to 90 minutes. The concession­ary ADB financing facility available for railway electrific­ation could be used. The Sahasara bus reform project that seeks to modernise the entire bus industry will also cost only 50% of the CEP-3. It has an EIRR of 21%.

But given the way those in power have benefited from expressway projects, the CEP- 3 project at four to five times the internatio­nal cost is likely to go ahead unless people put a permanent stop. The feasibilit­y studies estimate that the Rambukkana­Galagedera expressway would carry 6,000 vehicles a day when completed. Traffic growing at 4.5% p. a. will total 40 million vehicle movements over the 15 years government would have to pay this annuity. Even if it is built at the MCC annuity cost of $ 70 million per year, and if the expressway will have a 50% residual value in 15 years, a toll charge of Rs 4,850 is required from each vehicle to cover costs. This rate will be more than twenty times the current toll rates. Therefore, the non-users would have to bear the loss of this project for years to come.

The call to #stopexpres­sways

The time has come to change this destructiv­e culture that has pulled down Sri Lanka into the abyss of bankruptcy. This project is an excellent example of how it has happened over the last decade. It is projects such as these that the IMF must intervene to stop immediatel­y. They are economical­ly unproducti­ve and financiall­y unprofitab­le infrastruc­ture projects. The newly appointed Economic Advisory Council and those who will have the unenviable task of resurrecti­ng our economy must understand that it has been such showcase projects that have pulled the economy down in the first place. They should be replaced by alternativ­es such as those discussed above.

It is time for the hashtag generation to embark on a campaign to #stopexpres­sways. It is also time for the 400+ RDA engineers to serve the country over themselves. The RDA was a respected organisati­on up to the mid-2000s, but has now been corrupted systematic­ally to aid and abet projects that profit individual­s while suffocatin­g the Sri Lankan economy.

Doctors, lawyers, and other profession­als have protested against the corruption of their respective public institutio­ns. It is time that engineers and especially the highway engineers took serious note of how their esteemed profession has become subservien­t to the political masters and their engineer lackeys. It is time for all those who have directly or indirectly taken part in this highway robbery to apologise, reform and redeem our profession or choose to go down with the economy. Allowing the CEP to be awarded at this time is an acid test that will challenge your conscience and your courage.

 ?? ??
 ?? ?? This project's call for competitiv­e bids has now run into several transparen­cy issues.
This project's call for competitiv­e bids has now run into several transparen­cy issues.

Newspapers in English

Newspapers from Sri Lanka