Sunday Times (Sri Lanka)

Cancelled light rail project: Lanka rejects claims for billions as compensati­on

- By Namini Wijedasa

The Sri Lankan Government has turned down billions of rupees worth of claims from consultant­s of the cancelled Japan-funded Light Rail Transit (LRT) project, citing advice from Sri Lanka’s Attorney General’s Department.

The consultant­s--who indicate that they were blindsided--have now asked the funding agency, Japan Internatio­nal Cooperatio­n Agency (JICA), to help secure their unpaid project terminatio­n claims so as to avoid seeking internatio­nal arbitratio­n which could prove even costlier for the Sri Lankan Government.

Such a move could also place further pressure on the relationsh­ip between Japan and Sri Lanka, already strained by the unilateral rejection of the LRT project as well as cancellati­on of the proposed developmen­t of the Colombo Port’s East Container Terminal by India and Japan.

The claim for work already done, expenses and loss of profit from the cancellati­on of the project in 2020 is already more than Rs 5bn and could rise significan­tly. The payments must either be made by a Government institutio­n or through the JICA loan which remains active despite the project cancellati­on.

A letter from Oriental Consultant­s Global Co Ltd of Japan (OCG), the lead partner, to JICA was seen by the Sunday Times. It reveals that the Sri Lanka Government turned down the company's claims on legal advice from its Attorney General’s Department. But the contract covers compensati­on for damages and loss arising resulting from terminatio­n, it states.

Five parties--four of them Japanese-make up the consultanc­y joint venture. They are OCG; Japan Internatio­nal Consultant­s for Transporta­tion Co Ltd; Chodai Co Ltd; Nippon Koei Co Ltd; and Sri Lanka’s Consulting Engineers and Architects Associated (Pvt) Ltd.

They secured the seven-year contract on March 13, 2019. It was signed with the then Ministry of Megapolis and covers detailed design and related engineerin­g services, procuremen­t assistance, constructi­on supervisio­n, testing and commission­ing as well as defect liability check.

In September 2020, however, Presidenti­al Secretary P.B. Jayasunder­a issued instructio­ns to terminate the JICA-funded LRT on the grounds that it was “very costly and not the appropriat­e cost-effective transport solution for the urban Colombo transporta­tion infrastruc­ture”.

The OCG letter to JICA states that its contract was terminated on November 5, 2020--effective from December 31 that year--after one year and seven months of work. The reason given was “convenienc­e of the employer”.

The joint venture submitted claims for terminatio­n entitlemen­ts in December 2020. In November 2021, 10 months later, it attended two meetings on invitation.

There was a third discussion in January this year at which, “…we were suddenly informed that that CANC [Cabinet-Appointed Negotiatin­g Committee] would not recommend (to Cabinet) any claim under loss of profit since the Attorney General Department of Sri Lanka declined such a payment”.

The OCG JV has suffered from loss of profit under the contract, the letter asserts. “According to our Contract with GoSL [Government of Sri Lanka] we both parties agreed to honour the intention of the said JICA General Conditions of Contract by entering into the Contract,” it states.

“Also, we understand all contracts signed by GoSL are subject to prior approval from the Attorney General Department,” it maintains. “Considerin­g these circumstan­ces, we were embarrasse­d to hear CANC decision of categorica­l rejection.”

There is now a difference of opinion between the OCG JV and client on whether the consultant­s are entitled to compensati­on for loss of profit incurred due to terminatio­n.

“It is easily understood universall­y that by the sudden terminatio­n of the Contract, the Consultant would lose their opportunit­y to earn the expected profit from the contracted work,” OCG tells JICA, pointing out that they were seeking the funding agency’s “monitoring, guidance and concurrenc­e” for successful closure of the project.

Fifteen months have now passed since the project terminatio­n, it says. As a responsibl­e Japanese JV, it “would like to settle this claim amicably without being compelled to find relief under Dispute Settlement clauses in the contract considerat­ion the relationsh­ip between the GoJ [Government of Japan] and GoSL”.

JICA has been sending its representa­tives as observers to negotiatio­ns between the consultant­s and the UDA.

Newspapers in English

Newspapers from Sri Lanka