Sunday Times (Sri Lanka)

CEP 3: Continuing tussle between 2 bidders shows up Sri Lanka’s compromise­d procuremen­t process

- By Namini Wijedasa

The constructi­on consortium accused by a Chinese competitor of submitting an inflated bid for the Central Expressway Project’s third section (CEP 3) hit back this week, alleging that the claimed bid of Metallurgi­cal Corporatio­n of China (MCC) is at least 65 percent higher over the project’s lifecycle than its own offer.

Lanka Infrastruc­ture Developmen­t Consortium (LIDC) was tipped to sail away with the contract until MCC’s parent company, MCC Internatio­nal Incorporat­ion Ltd (MCCI), publicised a letter it wrote to President Gotabaya Rajapaksa alleging irregulari­ties in LIDC’s selection.

This letter, dated February 2022, claimed that MCC’s bid at US$ 1.05bn (Rs 367.49bn at the prevailing exchange rate) was significan­tly cheaper than what LIDC offered, which was US$ 1.87bn ( Rs 654.49bn). The difference was 56.7 percent higher.

But LIDC said in a statement this week that, not only is the MCC’s stated price unsubstant­iated--as their financial bid was never opened--LIDC was the “only successful, technicall­y qualified bidder for Section 3 of the Central Expressway Project from Rambukkana ( 12+ 890km) to Galagedara (32+450km)”.

The local consortium is made up of Access Engineerin­g ( which shares its head office address with LIDC), Maga Engineerin­g (Pvt) Ltd, Internatio­nal Constructi­on Consortium ( Pvt) Ltd, K D A Weerasingh­e & Co and NEM Constructi­on (Pvt) Ltd.

The tussle between the two bidders provides insight into how Sri Lanka’s procuremen­t process, particular­ly with regard to mammoth, high-cost projects, is routinely compromise­d. MCC was itself a beneficiar­y of the “unsolicite­d proposals” regime widely implemente­d between 2010 and 2015.

Neither LIDC nor MCCI have explained how they are so intimately knowledgea­ble about procuremen­t details that are required to remain confidenti­al from competing bidders. Had the Chinese not spilled the beans, even the price under negotiatio­n would’ve remained secret to the public with the Highways Ministry barrelling ahead with the costly project amidst a raging economic crisis.

Meetings of the Cabinetapp­ointed negotiatin­g committee ( CANC) were shifted from the Highways Ministry to the Labour Ministry and some officials were replaced with a Finance Ministry representa­t ive even being removed after he raised concerns about due process.

The project hangs in the balance, not least because of a Finance Ministry circular issued on Tuesday which ruled out new commitment­s for developmen­t projects-- including those using domestic funds, as proposed by LIDC. The Finance Ministry also prohibited the initiation of actions for acquisitio­n of lands or other assets in connection with projects where specific approval for commenceme­nt has not been obtained.

The local consortium now alleges that MCC made “massive blunders” in its bid; and that MCCI’s letter is “the first in a series of actions orchestrat­ed by MCC and their influentia­l local agents to discredit the LIDC’s bid and disrupt a legitimate Government procuremen­t process”.

LIDC also claimed that MCC did not submit a valid bid security; had cited the financial details and experience of the parent company (a separate legal entity) instead of its own; did not have sufficient experience to carry out the project; and requested payments in US dollars over 15 years.

The consortium was also “made to understand” that MCC did not avail itself of the opportunit­y to provide clarificat­ions--including submitting a valid bid bond--before the opening of providing financial bids.

The MCC letter to President Rajapaksa states, however, that when questioned whether its bid bond submitted through the Bank of China was ‘irrevocabl­e and on- demand’, “The

Bank of China submitted a letter reiteratin­g and confirming the submitted bid bond is irrevocabl­e and on-demand”.

It was not possible to verify these facts independen­tly. The Ministry of Highways--which was a key player in awarding unsolicite­d proposals to MCC in the past--remains non-transparen­t.

The LIDC statement this week also offers a technical comparison of its own price with the “claimed” price of MCC. Pricing has three components, it explains: constructi­on; operation and maintenanc­e; and cost of financing. Repayments were to be made over 15 years in 30 equal installmen­ts.

“LIDC’s price for the project has been quoted in Sri Lanka rupees whereas the price claimed by MCCI [sic] is quoted in US dollars,” it states, adding that its total offer for the constructi­on of CEP section 3 yields a per-kilometer ( km) price of Rs 5.6bn per km. CEP section 2 was completed by local contractor­s in 2021 for a perkm price of Rs 3.6bn per km.

By contrast, the average price of CEP section 1 that is presently being built by MCC is US$ 27mn (Rs 9.4bn at the prevailing exchange rate) per km, LIDC claims.

But this now calls to questio , had awarded the CEP 1 tender to MCC if, as LIDC indicates, the Chinese company’s price was inordinate­ly high in comparison with that of local contractor­s.

LIDC’s price for CEP 3 is significan­tly cheaper than MCC’s per-km cost for CEP 1 despite the third section being “more mountainou­s and challengin­g (including the necessity of a tunnel section and the impossibil­ity of creating a pilot road, etc) than that of both CEP section 1 and section 2”. On what costing formula, then, did the Highways Ministry select MCC for the much easier Section 1?

LIDC continues that its offer for CEP 3 is notwithsta­nding the fact that the price of key constructi­on inputs such as materials, labour and machinery have escalated on average more than 50% since the completion of CEP 2. Assuming there is still a reasonable profit margin, how much more inflated in price is CEP 1 that was awarded by the Highways Ministry to MCC?

Using certain parameters, including the semi-annuity payment mechanism, LIDC calculates its total project lifecycle cost to the Government to be Rs 354bn; and Rs 572.4bn based on MCCI’s claimed price (an exchange rate of Rs 545.13 per dollar is assumed as the 17-year average). This gives Sri Lanka a saving of Rs 227.4bn if LIDC gets the contract, it says.

“Based on the above calculatio­n, it is evident that MCCI’s claimed price is in excess of 65% (or LKR 227.4 Billion) of LIDC’s price over the project lifecycle with the potential to be even much higher,” LIDC maintains. “This is notwithsta­nding the fact that their real price is not known in the public (and the price they claim is just an unsubstant­iated statement), and that the Government of Sri Lanka (GOSL) will have to source invaluable foreign exchange (i.e. US dollars) to repay a foreign contractor of the project.”

“Furthermor­e, LIDC’s price of LKR 345 billion denotes the total cost of the project across its 17- year lifecycle, and does not reflect the time value of money and future depreciati­on of the rupee,” it adds. “In other words, if you apply a discount rate of 10% to account for the same, the present value of our bid (and the total cost to GOSL in today’s terms) is LKR 144.5 billion.”

LIDC also points to a battle between foreign contractor­s and the local constructi­on industry for projects. “Together, the five member companies directly employ over 25,000 members and sustain over 100,000 citizens, annually contributi­ng over LKR 100 billion to Sri Lanka’s GDP and LKR 2.5 billion to its tax base,” it states. “It is noteworthy to add here that the local constructi­on sector has also been embroiled in decade- long battle to wrestle our industry away from the strangleho­ld of foreign players.”

It draws attention to the concluding paragraph of MCCI’s letter to President Rajapaksa which calls for its Chinese subsidiary to be allowed to submit an engineerin­g, procuremen­t and constructi­on (EPC) contract or “unsolicite­d proposal” for the CEP 3 project.

“MCCI’s sole aim has been to sabotage an active public procuremen­t process ( which they also took part in and failed) and instead urge the GOSL to entertain an unsolicite­d proposal for the project, based on an unsubstant­iated claim or narrative,” LIDC asserts. “This is hiding in plain sight as their sole objective behind their campaign.”

 ?? ??

Newspapers in English

Newspapers from Sri Lanka