Bangkok Post

Egat plans new coal plant study

Krabi project’s EHIA to start in three months

- YUTHANA PRAIWAN

The Electricit­y Generating Authority of Thailand (Egat) says it will launch a new environmen­tal and health impact assessment (EHIA) for the planned coal-fired power plant in Krabi and an environmen­tal impact assessment (EIA) for its deep-sea port within three months.

The studies will take two years to complete and cause further delays in developing the facilities, said Egat governor Kornsit Pakchotano­n.

Prime Minister Prayut Chan-o-cha scrapped the previous EHIA earlier this month and ordered Egat to conduct a new one with greater input from nearby communitie­s.

Mr Kornsit said Egat plans to hire a different consulting firm to conduct the latest impact assessment­s for the 800-megawatt power plant and the deepsea port, to be located near the plant in the coastal province.

Bidding to conduct the assessment­s will be opened soon, he said.

After the new EHIA and EIA are completed, constructi­on will start around 2024, several years later than the previous 2021 deadline.

Mr Kornsit said that while there have been some concerns and requests from protesters and the opposition to switch from coal to gas, the change would not be easy to make.

He said if the policymake­rs eventually decided on gas over coal, Egat would need to develop not only a new power plant in the province, but also a gas pipeline, gas receiving terminal and floating gas storage unit — at a significan­t cost.

Mr Kornsit said there are no new gas fields in the Andaman Sea, while Thailand’s gas supply in the Gulf of Thailand is depleting sharply, making the country even more reliant on imported gas.

Moreover, the facilities for the gas-fired power plant, including the gas pipeline, would cause more damage to the marine ecosystem than the coal-fired plant, he said.

Regarding developmen­t of another 2,000MW coal-fired power plant, expected to be built in Thepa district in Songkhla province, he said operations are likely to be delayed to 2023, pushed back from 2022, as the land expropriat­ion process has lagged.

In order to seek ways to prevent possible blackouts and power shortages in the southern region due to delays of the planned coal-fired power plants, Egat is running a project to extend high-voltage power transmissi­on lines from the Thailand’s Central Plains or Malaysia, in the event the country needs to buy more power from its southern neighbour. The extension would transmit 700MW of power to the southern region.

 ?? SEKSAN ROJJANAMET­AKUN ?? Civic groups and academics attend a seminar on EIA/ EHIA public review, a mandatory process for any state projects that may cause environmen­tal impact to the community.
SEKSAN ROJJANAMET­AKUN Civic groups and academics attend a seminar on EIA/ EHIA public review, a mandatory process for any state projects that may cause environmen­tal impact to the community.

Newspapers in English

Newspapers from Thailand