Bangkok Post

Ratch pushes back start date of Laos dam

- YUTHANA PRAIWAN

The commercial operation date (COD) of the Xe-Pian Xe-Namnoy hydroelect­ric power project in Laos is postponed to late 2019 from February because of the collapse of a saddle dam on July 23, says SET-listed Ratchaburi Electricit­y Generating Holding Plc (Ratch).

The 410-megawatt project is located in Attapeu and Champasak provinces in southern Laos and operated by Xe-Pian XeNamnoy Power Co (PNPC), a joint venture of Ratch (25% stake), SK Engineerin­g and Constructi­on (26% stake), Korea Western Power (25% stake) and Lao Holding State Enterprise (24% stake).

Kijja Sripatthan­gkura, Ratch’s chief executive, said the project is claiming insurance from the collapse, which caused severe flooding along the Xe Pian River.

The accident affected several villages in Sanamxay district.

Detailed investigat­ions by Laotian authoritie­s and SK Engineerin­g & Constructi­on, as the lead shareholde­r, remain ongoing.

The 32-billion-baht hydroelect­ric power project is being constructe­d by leading South Korean companies. Constructi­on started in late 2013 and was projected to take five years, with a COD of February 2019.

Output from this project is to be transmitte­d to the Ubon Ratchathan­i substation in Thailand, through a 500-kilovolt grid. This power generation will help to secure power stability in northeast Thailand.

Of the 410MW power capacity, 370MW is to be distribute­d to the state-run Electricit­y Generating Authority of Thailand (Egat) under a 27-year power purchase agreement (PPA), with the remaining output sold to the Laos power grid.

In related news, SET-listed CK Power Plc (CKP), the power generation arm of the country’s second-largest constructi­on firm, SET-listed Ch. Karnchang Plc, has announced the COD of Laos’s Xayaburi hydropower plant is next October.

The Xayaburi project is located in northern Laos and is projected to have the largest hydroelect­ric power capacity in Southeast Asia at 1,285MW. The investment required is 150 billion baht.

Thanawat Trivisvave­t, CKP’s managing director, said the project is undergoing a trial run of the first electricit­y generator to Thailand, comprising 175MW, starting this month.

Trial runs will continue for all seven units, then the whole project is scheduled to begin operations.

Some 95% of the total power output is to be sold to Egat under a 29-year PPA, with the remaining output distribute­d to stateowned Electricit­e du Laos.

 ??  ?? The Xe-Pian Xe-Namnoy Dam is to supply a hydroelect­ric power plant in Laos.
The Xe-Pian Xe-Namnoy Dam is to supply a hydroelect­ric power plant in Laos.

Newspapers in English

Newspapers from Thailand