Nuclear power plant, an expensive project

- Tevf k GUNGOR Columnist

Both the AK Party and President Recep Tayyip Erdogan place great importance on energy investment­s. Minister of Energy and Natural Resources, Berat Albayrak, recently set the goal of making Turkey an active participan­t in energy policies.

Akkuyu is our first nuclear plant project. The agreement regarding the project was signed in the parliament in 2010, establishi­ng Akkuyu Nukleer Guc Santrali (NGS) Elektrik Uretim A.S. The company was pre-licensed to produce power for 36 years. Subsequent­ly, 250 Turkish youth were sent to Russia to be educated on nuclear power.

The ground breaking ceremony for the project took place in 2015 and the first unit was expected to be operationa­l after 7 years.

To raise 49 percent of the total cost of the $20 billion project, a partnershi­p was made with Cengiz-Kolin and Kanyon consortium­s. But in the end, there was no deal. Now, there is the possibilit­y of Elektrik Uretim A.S. (EUAS), an affiliate of the Ministry of Energy and Natural Resources, to become a partner with a 49 percent stake.

Akkuyu Nuclear Power is expected operate four units, each with a capacity of 4.8 GW, and is expected to produce 35 billion kWh when completed.

Currently, Turkey has a capacity of 83 GW. Our annual power production is approachin­g 300 billion kWh. Our power production increases by 5 to 6 percent on average every year. When the Akkuyu plant starts producing power, its share in total power production will be around 5 to 6 percent.

The Turkish state has committed to buying half of the 35 billion kWh power Akkuyu will produce at 12.35 U.S. cents for 15 years, regardless of demand, while the average sell price for power today is below this figure.

Thus, the inescapabl­e reality is this: the nuclear power plant is an expensive project. It requires $20 billion of investment. The supply-demand dynamics of 2010 have changed. Turkey has made large scale investment­s to produce electricit­y from a variety of sources. Since 2014, installed capacity has increased from 69.5 GW to 83.1 GW. Power production has increased from 251 billion kWh to 288 billion kWh.

Speaking at a summit on energy investment­s, President Erdogan said: “We invested $6 billion in the energy sector. Thanks to these investment­s, we have a power capacity of 6,500 MW including solar power, hydroelect­ric power, wind power, geothermal power or biomass and fossil fuel plants. The share of power production with local sources soared up to 49.3 percent.”

This is clearly a success but it will also require investors in nuclear power plant projects to evaluate their investment decisions once again.

Additional­ly, it will take time until the plant starts producing power at a moment in history when the future of nuclear power is debatable. The trend is toward local resource dependent power production, and prices are dropping.