NASMA RES­I­DENCES Lo­ca­tion Shar­jah, UAE

Vis­ited May 2018

Construction Week - - PROJECTS -

Arada’s devel­op­ment of Nasma Res­i­dences is mov­ing at a rapid pace to meet its Q4 2019 com­ple­tion tar­get. Khatib & Alami has com­pleted all in­fra­struc­ture de­signs for the project. En­abling works com­menced in Septem­ber 2017, with the main con­tract for Phase 1 awarded to In­ter­mass En­gi­neer­ing & Con­tract­ing. The contractor be­gan con­struc­tion of the project’s rst phase this Jan­uary. Arada has an­nounced that Phase 1 is 60% com­plete, with han­dover sched­uled for end of 2018. A semi-de­tached villa is the rst prop­erty com­pleted and open to the pub­lic as a show home.