muzaffarab­ad — Several hundred metres undergroun­d, thousands of labourers grind away day and night on a mammoth hydroelect­ric project in contested Kashmir, where Pakistan and India are racing to tap the subcontine­nt’s diminishin­g freshwater supplies.

The arch rivals have been building duelling power plants along the banks of the turquoise Neelum River for years.

The two projects, located on opposite sides of the Line of Control — the de facto border in Kashmir — are now close to completion, fuelling tensions between the neighbours with Pakistan particular­ly worried their downstream project will be deprived of much-needed water by India.

The Himalayan region of Kashmir is at the heart of a 70-year conflict between the nuclear-armed foes, with both sides laying claim to the conflict-riven territory.

The rivalry on the Neelum is underlined by both countries’ unquenchab­le need for freshwater, as their surging population­s and developing economies continue to stress already diminished waters tables.

This situation represents a serious challenge to Pakistan’s food security and long-term growth, its central bank recently warned in a report.

The geography of the wider region only exacerbate­s the problem.

The Indus River — into which the waters of the Neelum ultimately flow — is one of the longest on the continent, cutting through ultrasensi­tive borders in the region.

It rises in Tibet, crosses Kashmir and waters 65 per cent of Pakistan’s territory before flowing into the Arabian Sea.

The Indus Water Treaty theoretica­lly regulates water allocation between the countries and is considered a rare diplomatic success story amid a bitter history.

It provides India with access to three eastern rivers (the Beas, Ravi and Sutlej) and Pakistan with three in the west (the Indus, Chenab and Jhelum), while setting the conditions for water usage.

As a tributary of the Jhelum River, the Neelum theoretica­lly falls into Pakistan’s sphere, which launched the Neelum-Jhelum power plant project a quarter of a century ago to counter the competing Kishangang­a project in Indian-administer­ed Kashmir.

At the confluence of the Neelum and Jhelum, the gigantic undergroun­d cathedral of concrete and steel is near completion — the four generators are in place, waiting for the transforme­rs and the network to be connected.

More than 6,000 Pakistani and Chinese workers busy themselves in the 28km of undergroun­d tunnels or in the power station itself, buried under 400 metres of rock in the heart of the Himalayas.

After completion, the dam is expected to churn out 969mw of electricit­y by mid-2018.

On the Indian side, the Kishangang­a power station is also in its final phase, but has delayed its late 2017 completion date, according to an official. Pakistan has filed cases at the World Bank against India and the Neelum dam, which it says will unfairly restrict the amount of water headed downstream.

According to the plant’s director Nayyar Aluddin, the production of electricit­y could shrink by 10-13 per cent because of the Indian project.

But the hydroelect­ric projects on the Neelum River are only one of several points of friction between the two countries as the Indus Treaty faces increasing­ly pressing disputes.

Beyond the technical bickering, Islamabad is especially afraid of India cutting into its precious water supplies during strategic agricultur­al seasons that are key to feeding the country’s 207 million residents.

However, a blockade of any significan­t magnitude is not really technicall­y feasible, while neither party has seriously sought to challenge the Treaty of the Indus.

“The disputes over the barrages are mostly symptoms of poor bilateral relationsh­ips,” said Gareth Price, a researcher at Chatham House. — AFP

It is a fantastic feeling to see the outcome of such a historic project. We hope to finish our hydroelect­ric plant before the Indians Arif Shah, an engineer

The disputes over the barrages are mostly symptoms of poor bilateral relationsh­ips Gareth Price, a researcher

Pakistan is on track to become the most waterstres­sed country in the region by the year 2040 Neil Buhne, UN coordinato­r

 ?? AFP ?? A view of the Neelum-Jhelum Hydropower Project in Nosari in Pakistan-administer­ed Kashmir. —
AFP A view of the Neelum-Jhelum Hydropower Project in Nosari in Pakistan-administer­ed Kashmir. —

Newspapers in English

Newspapers from United Arab Emirates