MCA

-

MCA was recently awarded a contract with ECG for the LV Equipment for the new Sandrado Gold Plant located in Burkino Faso.

The project included the supply of all the low voltage control centres and mobile substation­s. This mine will be supplied with five of MCA’s Sivacon S8 Low Voltage MCC’s installed within containeri­sed substation­s.

These substation­s will be complete with VESDA fire protection systems, Aircons and pressurisa­tion units, Schneider

APC UPS’s, and all small power and lighting equipment. These units will be pre-commission­ed and tested in Johannesbu­rg in July and shipped to site in August 2019, ready to run.

E Dion@motorcontr­ol.co.za www.motorcontr­ol.co.za