NEW CAR TIMELINE
JULY 1 2017
Finalise initial concept for 2018 car. Start dedicated 2018 windtunnel R&D. Begin dedicated component layout design. Start dedicated design of gearbox, uprights, fuel tank – all long-term manufacturing items.
NOVEMBER 1 2017
Start to machine chassis pattern.
MID-NOVEMBER 2017
Start lay-up of chassis mould.
DECEMBER 1 2017
Start lay-up of first chassis. Other components like nose, rollover bar, side-impact components to be manufactured at the same time.
JANUARY 1 2018
FIA chassis crash and impact tests using the above components. All components to start to filter into the factory, with large components first.
FEBRUARY 1 2018
Start test-car assembly. Sort out final wiring and piping-system design. Commitment to final testcar specification.
FEBRUARY 20 2018
Load the cars and head to Barcelona for pre-season testing, fingers crossed.