SO HOW DOES IT WORK?

-

Day 1

Before work commences the space is cleared, door frames are wrapped with foam padding and any furniture, lighting etc is fully protected in plastic.

Day 1-3

There is minimum disruption when installing a Spiral Cellar. The team excavates a hole for the cellar by hand which keeps noisy machinery off site – and the neighbours happy.

Day 4

The completed hole is fitted with steel shuttering rings to give the cellar structure. The ring is then lined with a robust waterproof liner.

Day 5

A uniquely designed modular system of interlocki­ng concrete bins and steps, complete the cellar constructi­on.

Day 8

Additional items such as stair treads and LED lights are fitted. The door is carefully fitted and protected while the floor in the room is re-laid and finished around the cellar. With the installati­on complete, the cellar is ready to be filled with wine and enjoyed.

 ??  ??
 ??  ??
 ??  ??
 ??  ??