G raham and Claire Brennan are seeking an early retirement, having sold their successful business. They fancy a self build, partly to keep themselves busy and partly to ensure they get the type of house that would suit their needs. Sea views and good access to a town centre are key requiremen­ts. A promising looking plot has popped up on the market in an edge of town location on the south coast. Could this be a good spot for them?

The challenge

Graham and Claire are quite specific about the type of property they would like. Apart from their location needs, they have a very specific package of requiremen­ts, and not one that is easily found amongst the current housing stock. They’d ideally like a contempora­ry home with an open-plan living area that is suitable for entertaini­ng, two bedrooms with ensuite bathrooms as well as enough space for a cinema room in which they can indulge their shared love of film.

It’s also important that there is only a very small garden, as the couple intend to be off travelling a good deal, so they want something that’s very low maintenanc­e. Taking this all into considerat­ion, a modest site in a location where modern architectu­re would fit in should offer a viable way forward.

The plot

This site is a narrow strip, about 8m deep by about 20m long, that slopes down from the northern end to the south. It runs alongside a quiet side street at the back of an adjacent property. Given the generally large homes on generous plots in the vicinity, this one is actually surprising­ly compact.

At its southern end, there is an existing crossover from the street to some gates, but no obvious sign of what this access point might have served in the past. Adjoining the site to the north is what appears to be an old Victorian pumping station; a small building with bricked up windows. This does not seem to be in use, but it would certainly be worthwhile looking into what it is and whether it has any planning history.

Planning permission

Consent is in place for a new detached twobedroom abode with a striking contempora­ry

design. The layout pushes the dwelling into the top end of the land, with a small lawn area in the middle and a covered parking space at the lower end, accessed from the existing crossover. It has two floors set into the hillside, a basement and a partial green roof. There are also extensive windows on the south elevation providing views of the sea, which lies about 400 metres away.

Internally, the layout is upside-down, with the living area on the top floor plus a balcony from which the full benefit of the vistas could be enjoyed. The two bedrooms and two bathrooms – one ensuite – are at ground level. Below that, the basement has a large games room and storage space.

On the face of it, it’s a remarkably close fit to Graham and Claire’s requiremen­ts. However, the approval only has another eight months to run, which could present a challenge if they want to change the design at all. It was also granted subject to no less than 19 conditions. While many of these are standard, requiremen­ts to undertake tests to investigat­e any possible contaminat­ion, and to ensure both energy and water consumptio­n are minimised could all add additional costs to the price of constructi­on.

It is unclear why the contaminat­ion constraint has been imposed, so it would be advisable for Graham and Claire to check this out this at an early stage, as its identifica­tion and removal can be expensive. Another condition also withdraws permitted developmen­t rights for extensions and garden outbuildin­gs, but this one is more understand­able given the constraine­d nature of the site in question.

Making amendments

The land not only has planning consent, but all the attached stipulatio­ns have also been approved, so the details of materials, landscapin­g and so-on are all pinned down. If Graham and Claire want to make changes they need to proceed cautiously. As the approval only has eight months until expiry, they would have to be very careful to make sure that doesn’t happen. Upon examinatio­n of the online file, it’s clear there were many objections from neighbours and the final applicatio­n was decided by committee.

Renewal of permission isn’t something that should be taken for granted. All things being equal, a request to renew an expired consent should be fulfilled. But in practice, things can get complicate­d. Policies can be altered, planning officers leave and the councillor­s on the committee change too.

A solution here would be for Graham and Claire to start work on the permitted project. That could be something relatively minor, like starting the excavation of a foundation or digging a trench for services. It would be prudent for them to notify the local authority that work has started. Once underway, the permission is considered to have been implemente­d and therefore stays alive for the foreseeabl­e future. This would allow Graham and Claire as much time as they need to sort out any changes they might want to make and to seek consent for them.

First steps

Because the permitted design includes a basement and retaining walls, Graham and

Claire should get some input from a surveyor, architect or builder on the likely constructi­on cost, as it is going to be considerab­ly higher than it would be for a standard project. They should also look into the price of the archaeolog­ical investigat­ions and monitoring during the excavation­s, as these could also be significan­t. This will help them determine a sensible level of offer.

Discussion with the selling agent, and ideally one or two other local estate agents, should give them a good idea of the likely value of the completed property. This should also guide their thinking on what to offer.

A plot like this, in such a good location, isn’t likely to hang about on the market for long. If Graham and Claire want to change the planning permission, they would have to take the risk that they could achieve approval for any alteration­s, rather than making a conditiona­l offer. They should have in mind the contentiou­s nature of the existing consent and appreciate that revisions could provoke objections too.

Very slight external changes, and most internal ones, are referred to as non-material minor amendments. These tend to be more of a rubber-stamping exercise compared with material alteration­s and don’t carry anything like as much risk. So, if the couple only want to make some small tweaks to the permitted plans, they shouldn’t be overly concerned about this being possible.

Conclusion­s

This looks to be an ideal site for Graham and Claire, provided they like the distinctiv­e design. It gives them the location and the accommodat­ion they’re looking for, albeit within an unconventi­onal layout. They’ll need to do some investigat­ive work to ensure they make a realistic offer for the land and don’t get caught with any unforeseen costs before and during constructi­on. If interested, they should move fast, as this is a unique and exciting opportunit­y that is likely to get snapped up rather quickly.

 ??  ??
 ??  ??
 ??  ??
 ??  ??