Build It

Prime costs explained

Tim Doherty reveals why it’s important to get a handle on these terms when it comes to budgeting and calling in quotes for your home building project

-

Get to grips with the essential constructi­on jargon and make sure you don’t slip up when pricing your project

From planning through to completion, as you move forward on the path to your self build home, you’re sure to encounter all sorts of constructi­on jargon. Two such terms are ‘prime costs’ and the closely related ‘provisiona­l sums’ – phrases you’re likely to run into when you start to call in quotes from builders.

A prime cost is the total of all the direct costs associated with a particular constructi­on activity. So, if a builder calls in a specialist sub-contractor to carry out some work, such as re-rendering an external wall, the prime cost would be the sub-contractor’s invoice to that builder for the labour, the materials and plant provided. But if the builder carries out the work using their own labour, then the prime cost would be worked out differentl­y: the proportion­ate costs for their direct labour plus any scaffold required, the use of a mixer and the delivered cost of the raw materials.

These are ‘true’ prime costs, and don’t allow for any contractor back-office expenditur­e or any profit for processing the work. In practice, however, you’ll probably encounter the term in a slightly different context on your home building project: namely as informed (to a greater or lesser extent) estimates for some parts of the work.

Prime costs vs provisiona­l sums

When a project’s specificat­ion is first being drawn up, there might not be sufficient details from the architect or client for a surveyor or builder to fully flesh out what’s required. This makes it difficult to accurately quote for a job, as they can’t be expected to give a fixed price when the brief is still vague. In these situations, they will allocate a cost to be included: either as prime cost sum (PC sum) or a provisiona­l sum

(PS). But what’s the difference between the two?

The Royal Institutio­n of Chartered Surveyors (RICS) provides subtle advice on the matter as part of a glossary included in its cost reporting guidance. It says a prime cost sum is used for “the quantities of work whose extent is known, but whose specificat­ion has yet to be determined.” A good example would be windows and external doors, where you know the physical number required but the type, quality level and manufactur­er is yet to be decided. The contractor will be expecting to procure the final window selection once agreed, but will also expect to apply their overheads and profit to the eventual prime cost invoice from the supplier.

The RICS gives two categories for provisiona­l sums – defined and undefined. Where a PS is defined, the sum provided is for work not completely designed but where the following informatio­n is known: “the nature and constructi­on of the work, a statement of how and where the work will be fixed to the building and what other work may be fixed to it, quantities that indicate the scope and extent of the work and, finally, any specific and identified limitation­s.”

So, an example of a defined provisiona­l sum might be a conservato­ry that’s outlined on the planning drawings to show its scope, along with notes indicating brick plinth walls, foundation­s and a floor slab – but precious little else. In this case, the client will expect the contractor to have included an allowance for appropriat­e programmin­g, planning and pricing in their quote. Therefore, once the contractor has received the missing specificat­ion details, there must be an opportunit­y for them to revise their provisiona­l sum accordingl­y. You should then only instruct them to proceed with the works once the final figure has been agreed.

Undefined provisiona­l sums are used where the detail just isn’t known. For instance, a nominal figure of £30,000 might be allocated to a detached garage so the overall budget can at least reference a desirable, but less immediate, part of the project. In this scenario, you can’t expect the contractor to have identified specific procuremen­t costs. So, if you instruct them to do the work, it will need to be priced up from scratch.

Why prime costs & provisiona­l sums are important

Sending a set of building control drawings to a contractor and asking for a price is a recipe for disaster. Instead, a client should carefully prepare (either themselves or using their profession­al team) a detailed specificat­ion and schedule of works to accompany the plans. Nobody, however, will know the full extent of their project’s specificat­ion at the time of appointing contractor­s. So, where gaps exist, prime costs and provisiona­l sums should be inserted.

The skill is in allocating the right amount of money, so that when the project budget is aggregated, a realistic figure will be arrived at. If the total cost is too high, then this is the stage to start your value engineerin­g (and absolutely not once work has started, as this will lead to price hikes).

You should also agree at tender (quote) stage what mechanism will be used to calculate overheads and profit (OH&P) from the main contractor on any prime cost sums or project variations. Typically, this will amount to an uplift in the prime cost of somewhere between 10% and 20%.

Valuing prime costs sums

When drawing up a PC sum, the surveyor or contractor will draw on experience and known rates to try to generate a

reasonably accurate quote. Let’s return to our window example here. In this case, the eventual cost will largely come down to the invoice from the supplier/manufactur­er.

For our purposes, we’ll assume the client wants off-theshelf, double-glazed factory painted timber windows and that there will be 10 of these. A sensible and fair way to control costs while keeping options open for the client would be for the tender documents to include a prime cost sum. If the windows are supplied at £400 each, then you might be quoted a total of £4,500 including an allowance of £500 for the contractor’s OH&P.

Say the client ultimately goes on to specify composite windows instead, at a cost closer to £600 each. In this case, the eventual supplier invoice to the contractor for the 10 units would be £6,000. They would reasonably expect to recover this, plus their OH&P, from the client using the agreed percentage uplift negotiated at the tender stage.

A different example might be why there’s a prime cost sum for creating a veranda and balustrade to be completed by the contractor’s own carpenters, but the exact spec of decking and spindles has not yet been finally agreed. The valuation of this PC sum would be based on the supplier invoice for the materials, the appropriat­e OH&P percentage markup and the addition of labour using the all-in-rates (see box, above) for the amount of time the work takes – with no further OH&P markup. This total cost would then be substitute­d into the contract instead of the original PC sum. Simples!

Opposite: Kitchens are a common area where PC sums are used. The contractor might base their initial pricing on sourcing the products from a tried-and-tested trade supplier and using their own labour – and then update the costs once you agree a final spec

 ??  ??

Newspapers in English

Newspapers from United Kingdom