Campbeltown Courier

Major milestone in Crossaig pylon powerline project

-

A major constructi­on milestone was reached in the multi-million-pound powerline constructi­on project between Lochgilphe­ad and Crossaig, on Kintyre’s east coast, with the first towers installed.

SSEN Transmissi­on has installed the first two of 149 steel towers for the replacemen­t overhead line which will span across 45 kilometres between Port Ann and Crossaig Substation.

Teams have also made great progress with the installati­on of 48 kilometres of access track and 21 of the tower foundation­s as part of the ongoing project. This is the second phase in the wider Inveraray to Crossaig powerline upgrade, with the first phase – Inveraray to Port Ann – energised in July 2021.

The new powerline will replace the existing infrastruc­ture in the area, which was originally built in the 1950s and is now reaching the end of its operating life.

SSEN Transmissi­on says the new replacemen­t powerline will provide a new robust and reliable transmissi­on network across the region and will serve as one of the transmissi­on network’s main arteries in the west of Scotland. The energy company added that it was one of the most significan­t electricit­y network investment­s in the region in decades.

Once complete, the powerline will operate at 132kV, with the capacity to be upgraded to 275kV in the future, forming a part of SSEN Transmissi­on’s Argyll 275kV strategy.

This will see the electricit­y transmissi­on network in the region reinforced to enable the connection of more than 600 MW of new renewable generation, helping in the transition to net zero emissions and the fight against the climate emergency.

‘This is a major milestone in our ongoing project between Port Ann and Crossaig, and I’m delighted to see the first of 149 towers installed as part of this highly complex engineerin­g project,’ said David Auld, project manager for SSEN Transmissi­on. ‘Once complete, it will not only provide a more resilient transmissi­on network in Argyll, but also provide increased capacity to allow more renewable electricit­y generation to be connected to the grid – allowing clean energy to be transporte­d to where it is needed most and assist in the fight against the climate emergency.

‘As a stakeholde­r-led business, we’ve been working closely with the local community and stakeholde­rs to share informatio­n with them about the project and to help mitigate the impacts of our activities, and we thank them for their continued patience and understand­ing as we deliver this critical national infrastruc­ture which will serve the region for many decades to come.’

 ?? ?? The first two towers have been installed during phase two of the new InverarayC­rossaig overhead line.
The first two towers have been installed during phase two of the new InverarayC­rossaig overhead line.

Newspapers in English

Newspapers from United Kingdom