Campbeltown Courier

Burnside Square is transforme­d

-

The installati­on of a storage tank under Burnside Square began on Monday, as good progress continues to be made on the Campbeltow­n Flood Protection Scheme works.

That is according to Argyll and Bute Council’s roads and infrastruc­ture services team which issued an update on the £15 million project this week.

As part of the scheme, which is 80 per cent funded by the Scottish Government and 20 per cent funded by the council, a variety of measures are being put in place to reduce the impact of flooding on residents and businesses in the town.

In the last few months, contractor­s have installed new pipelines under many of the town’s roads to increase the capacity of the drainage sys- tem so that it can cope better with heavy rainfall.

Many of these pipes will lead into the new storage tank underneath Burnside Square. This tank will safely store water and allow it to slowly discharge.

The Burnside Square part of the project kicked off in earnest when contractor­s returned to work on Thursday January 5 following the Christmas and New Year break.

Since then, they have excavated the square ahead of starting work to install the tank which involves the use of a piling rig.

“We had hoped to save some of the old trees from the square for possible replanting elsewhere but unfortunat­ely they were not able to be saved," said a roads and infrastruc­ture services spokespers­on.

“We are continuing to work on design options for the reinstatem­ent of the square following the public consultati­on which concluded in favour of a flexible space which could be used for events, and for parking when not in use for events.

“We would expect to have these updated designs for sharing shortly.”

Site investigat­ion works into the creation of a safe water storage reservoir at Millknowe also began on Monday, with the main works due to start in the spring.

Given its location and the type of works involved, this part of the project is expected to be the least disruptive.

Under phase one of the project, which began in September last year, new pipelines and safe water storage ponds are being created in the Meadows area.

This should be finished in June; contractor­s are currently waiting for the area to dry out before topsoiling the ponds and reinstatin­g the fields.

This is expected to be followed by resurfacin­g of the roads around the works.

A public pop-up informatio­n event will soon be held to update the community on plans to install a new culvert under the existing road at Dalaruan Street. The contractor, design team and council will all be present to discuss the works in detail, the phasing plan and how disruption to the community will be minimised.

 ?? 50_c05burnsid­esquare01 ?? Burnside Square is unrecognis­able is work is carried out to install a storage tank beneath it.
50_c05burnsid­esquare01 Burnside Square is unrecognis­able is work is carried out to install a storage tank beneath it.

Newspapers in English

Newspapers from United Kingdom