Roadworks bill set to go up by £3.3bn

- BY NEIL LANCEFIELD

WORK enhancing A-roads and motorways in England will cost an estimated £3.3billion extra, a report has found.

The National Audit Office said that 39 projects would not be delivered within budget.

The public spending watchdog also noted that 33 projects are behind schedule with an average delay of 12 months.

The report warned: “This will leave road users with an underperfo­rming road network for longer.”

Delays have been made worse by the pandemic as well as planning permission difficulti­es.

Head of the NAO Gareth Davies said: “Neverthele­ss, more could have been done to manage risks.”