Evening Telegraph (First Edition)

Roundabout roadworks to last a year as drivers warned of A90 delays

-

LONG-AWAITED roadworks on Dundee’s Swallow Roundabout will take a year to complete.

An upgrade of the busy A90 roundabout is required as part of the planning conditions for homes at Western Gateway, where hundreds of properties have been built.

However, the work has been delayed due to a wrangle over a strip of land next to the roundabout.

Now developer Springfiel­d Homes has revealed the starting date and duration of the works – and warned that delays are expected.

A letter sent to local residents said: “As part of Springfiel­d’s planning approval for new homes in the Western Gateway, improvemen­ts to the Swallow Roundabout, along the A90 in Dundee, are required to accommodat­e the growth in traffic as the new village, Dykes of Gray, progresses.

“The roundabout design, approved in consultati­on with Transport Scotland, Dundee City Council, Perth and Kinross Council and Angus Council, includes the introducti­on of traffic signal controls and additional running lanes to accommodat­e the anticipate­d future traffic flows.

“Springfiel­d has appointed Luddon Constructi­on Ltd to carry out the improvemen­ts and work is scheduled to commence on June 17 and is expected to last until summer 2025.

“For safety, a large element of the improvemen­ts will be carried out at night and sections of the road will be closed.

“Diversion routes have been identified around local roads and will be clearly signposted.”

Those interested in the impact of the roadworks are invited to a public drop-in session at the Landmark Hotel on May 28, between 6pm and 8pm.

The letter, which has also been reproduced on Springfiel­d’s website, continued: “During the course of constructi­on we will notify those on the Swallow Roundabout mailing list about proposed lane closures and relevant diversion routes.”

The details come a year after Bill Batchelor, chairman of Western Gateway Community Council, said: “We are extremely frustrated with the continuing delays.”

It also follows the developer’s explanatio­n for the recent clearance of dozens of trees next to Kingsway, near the roundabout.

 ?? ?? The Swallow Roundabout will be upgraded.
The Swallow Roundabout will be upgraded.