Mowi plans upgrade for Blar Mhor
LEADING salmon producer Mowi is investing in an upgrade for its Blar Mhor processing facility in Fort William. The project will take the plant up to a capacity of more than 80,000 tonnes.
Mowi said that building work is expected to start this year, for completion in the second half of 2022. Meanwhile, Scott Nolan, Processing Development Manager for Mowi Scotland, has been promoted to the position of Processing Director to manage the project.
The new-look Blar Mhor will feature robotic technology for handling and grading salmon and production will continue throughout the upgrade project.