Heritage Railway

Track re-laid in latest phase of SVR Falling Sands viaduct refurbishm­ent

- By Robin Jones

THE £1.32 million project to refurbish the Severn Valley Railway’s Falling Sands viaduct is on schedule, with track re-laid across it as part of the completion of the first phase.

Work began at the end of last year to tackle the internal structure of the 1877-built viaduct, in order to improve the drainage and incorporat­e a waterproof layer.

The project has been financed by £925,600 from the National Lottery Heritage Fund and by the railway itself, which raised matched funding of £397,000 through its Helping Hands for

Falling Sands campaign.

The first phase saw 200mm-thick panels of fibre-reinforced concrete cast over the arches and two coats of a special bituminous paint poured over the concrete and the walls. On top of the waterproof­ing, a layer of chippings was laid to permit water to migrate to the low points and out through pipes.

Contractor Walsh took the full brunt of storms Ciara and Denis to succeed again the odds.

Infrastruc­ture volunteer Nick Yarwood said: “The project has progressed ahead of programme, due in part to an exceptiona­lly mild winter. The greatest risk was prolonged freezing or snowfall interferin­g with concreting and waterproof­ing.

“Waterproof­ing needed seven days to complete and was also vulnerable to rain. With good programmin­g and a week of calm dry weather, it all went to plan.”

Nearly 3000 tons of fill material was tipped back into place and compacted prior to the re-laying of ballast. Concrete troughs were also laid to accommodat­e signal cables.

By late March, the track was being re-laid ready for the scheduled reopening of the line between Bewdley and Kiddermins­ter in early April. However, those plans were overtaken by the coronaviru­s pandemic. This resulted in the railway cancelling its Easter holiday activities, the April 16-19 spring steam gala and the 50th anniversar­y celebratio­ns in May, among other events.

The second phase of the viaduct refurbishm­ent, to be started later this year, will see contractor­s use rope access to replace damaged bricks and repoint the mortar on the outside walls and arches.

The 132-yard red brick viaduct, otherwise known as Bridge 3, takes the railway 64ft above the Staffordsh­ire & Worcesters­hire Canal and River Stour.

 ??  ?? Track being re-laid on Falling Sands viaduct a mile west of Kiddermins­ter on March 21.
Track being re-laid on Falling Sands viaduct a mile west of Kiddermins­ter on March 21.
 ??  ?? BRENT CLEETON/SVR
BRENT CLEETON/SVR
 ??  ?? Concrete pumping and placement underway earlier. NICK YARWOOD/SVR
Concrete pumping and placement underway earlier. NICK YARWOOD/SVR

Newspapers in English

Newspapers from United Kingdom