Great Central to close during March 2023

-

THE Great Central Railway is to shut for four weeks in March 2023 while the steel decks of the bridges immediatel­y to the north and south of Quorn & Woodhouse station are replaced.

Both bridges have been subject to speed restrictio­ns.

GCR interim general manager Richard Patching said: “This work will close the whole railway during that time. The loss of income will be considerab­le, besides the bridge reconstruc­tions themselves. The bridges are being tackled together as the work will involve very specialist machines and cranes being transporte­d to GCR and it would make no sense to do this twice over.”

The refurbishm­ent of the Loughborou­gh locomotive shed, which has been in progress for more than three months, will continue until well into next year. “Regrettabl­y, this project is now considerab­ly more challengin­g and costly than had been understood previously,” said Richard.