Homebuilding & Renovating

a race against time

Despite a lengthy planning process, Lesley and David Lennox have built a timber frame home that combines contempora­ry design with traditiona­l details — completing the build in less than a year in time for a very important event

-

Having previously built a house in 2009 and finding that they thoroughly enjoyed the process, Lesley and David Lennox decided they wanted to do it all again.

“We knew we wanted another building project,” says Lesley. “But nothing that suited us was coming up, so we expanded our search area and found our plot.”

Extending to one acre and hiding a rundown 1950s bungalow beneath 12 foothigh brambles, the plot was set within a pretty Hampshire village, in a conservati­on area and had formerly made up part of the garden of a 19th-century manor house.

“A group of bungalows were built in the garden in the 1950s and ours was the only one left untouched,” explains Lesley. “It was just a little bungalow in an acre of wilderness — but we could see its potential.”

Lesley and David took the brave decision to live in the bungalow, which had stood untouched for three years — it ended up being their home for the next two years.

“It was in an awful condition,” says Lesley. “We moved in during winter. The central heating system had been condemned but thankfully a local heating engineer got it going eventually. We spent that first winter sitting with blankets over our knees.

“We also discovered that there had been some little four-legged creatures living here too. The rodents had chewed all the woodwork and the kitchen was completely infested — the whole thing had to be ripped out and replaced with temporary facilities.”

Lesley and David also found that the bungalow’s foundation­s were moving, leaving gaping holes beneath the skirting boards.

planning

“We knew that planning wasn’t going to be easy as we are in a conservati­on area, but we were hopeful as other new properties had been built in the village,” says Lesley. Having applied twice, unsuccessf­ully, for planning – the second time with plans that the planners had led them to believe would be acceptable – Lesley and David came across self-build homes specialist Potton.

“We hadn’t realised that you could have a completely bespoke design from Potton,” says Lesley. “As soon as we met the designer, Sean, we had a good rapport, plus he had experience of conservati­on areas and knew the local planning department.”

Working alongside Sean, Lesley and David came up with a brief for their new home. “Because of the village setting, we didn’t want anything outrageous­ly modern. But we also didn’t want a replica of what we had built before,” explains Lesley.

“We felt that as we were building from scratch, we wanted the house that we want-

ed, not what the planning department wanted — we didn’t want to build a box! We were keen to have five bedrooms, all with en suites, as we like to have guests. We also wanted an open, sociable kitchen.”

On the advice of Sean, Lesley and David went for pre-approval planning, submitting a basic design. They then went in with their full plans and, after some tweaking, the plans were sent to the local area committee and finally approved in October 2015.

“We were working to a deadline,” says Lesley. “Our eldest daughter was getting married in October 2016. She lives in Hong Kong and needed somewhere to stay, along with some of the wedding guests. Our deadline was a year to the day we received planning permission.”

Although Lesley and David both work full-time, they decided to take on the sizeable task of project managing the build.

Once the old bungalow was demolished, they moved into a caravan on site — their home for the next nine months.

“There were a couple of challenges that we were faced with early on,” says Lesley. “Firstly we had to recycle 90% of the materials from the demolished bungalow. Secondly, with the plot being so close to the river and because of the soil type, we had to include six-and-a-half metres of piling beneath the new house.

“Also, as the new house is a prefab type of constructi­on, the site needed to be as level as possible, so it [the foundation­s and ground floor slab] was raised at the rear.”

Even before the demolition, Lesley and David had made decisions on all the internal fittings, as well as the layouts. “We have found that the further you get into a build, the more stressful it becomes, so by deciding on the finer details early on, the fraught decision-making process was removed. The footings went in in December 2015 and the delivery date for the timber frame was February 2016.”

Despite falling two weeks behind over Christmas, Lesley and David “took the bull by the horns” and got it all back on track.

“We thought the house would take some time to construct, but by the end of the first day we were walking around the foundation­s, seeing where walls were and even looking out of the new window apertures.

“Our 325m2 house was built in 12 working days by five men! Within those days, the roofers had begun felting the roof and the house was watertight within a month.”

The new house has been clad using a combinatio­n of through-coloured render and larch, while the slate roof and brick ‘dwarf wall’ that runs around the base of the perimeter adds a more traditiona­l feel.

Reflecting the sloping nature of the site, to the rear of the property is an expansive timber deck — it’s around 70m2 in total.

Two balconies add both interest and a practical feature to the rear elevation. “We like being able to have a covered external space,” explains Lesley. “We asked for two balconies on our planning approval but were originally refused, so we were going to just have large windows.

“Then the conservati­on officer flagged up the fact that the living room bifolds could cause overheatin­g, so came up with the solution of a balcony above that could act as a shade — the 5m-wide bifolds in the living room basically dictated the size of the balcony above.”

Internally, Lesley and David’s desire for an open plan and sociable kitchen diner has been realised. “We could spend all our time in there,” says Lesley. “There was a wall planned between the kitchen and dining area, but we got rid of it to make it all open.”

A formal living space has also been included to provide a quiet separate space. The first floor is accessed by a grand oak and glass staircase, leading to a vaulted landing area with Douglas fir beams.

Although underfloor heating – powered by an air source heat pump – has been installed throughout, Lesley says that they only ever need it on low, even in winter.

“The house is so well insulated there is not much need for heating,” she says. “We have the flue in place for a woodburner because we like the ambience they give, and we may add some photovolta­ic panels at some point, too. We have learnt from our previous projects, so there isn’t much we would change.”

And the October deadline? “We moved in five weeks before the wedding,” says Lesley. “We had a house full of people and it ended up being a base for family and guests from all over the world to stay.” Lesley and David’s kitchen, from Optiplan, is a Shaker-style design. Along with the central island, with seating, the space is open to a large dining area and living space.

 ??  ??

Newspapers in English

Newspapers from United Kingdom