Self-build Project Planner
However you’re getting it built, you’ll need to know how a house is constructed. Here is our definitive guide to each stage of the process
A step-by-step guide to building your own home
Prepare Site
➳ Groundworkers create site access
➳ Clear site and strip vegetable soil; stacking material to be retained out of the way
➳ Set up site hut and equip with drawings and safety equipment
➳ Set up toilet
➳ Secure lock-up/lorry container (hired in or purchased) to be positioned
➳ Water board to bring supply to stopcock on boundary
➳ Plumber to connect water standpipe
➳ Surveyor marks out building on cleared site and transfers the lines to profiles well clear of any construction work
➳ Bring in bricks and blocks and stack clear of future construction
➳ Set up mixer station close to cement store and sand heap
Foundations/oversite
➳ Groundworkers excavate foundations
➳ Wait for approval of building control and warranty inspectors
➳ Position any reinforcement bars, mesh or cages in the trenches
➳ Position any compressible material or slip membranes required within the trenches
➳ Lay ducts for services to enter through the foundations
➳ Arrange foot scaffold if necessary and shutter for any steps in the foundations
➳ Pour concrete footings and tamp to level
➳ Obtain approval from building/warranty inspectors to proceed
➳ Bricklayers build up foundation blockwork to damp-proof course
➳ Install cranked air vents
➳ Install drainage exit lintels
➳ Fill cavities with lean-mix concrete to level with external ground level
➳ Bed and lay damp-proof courses, linking these with any radon membranes or barriers
Start the Superstructure
➳ Groundworkers to dig service trenches and lay pipes and ducts to proposed stopcock/meter positions
➳ Load out concrete floor beams to each bay and position
➳ Install drainage and vent pipes proud of the oversite
➳ Infill floor beams with blocks
➳ Lay coursing blocks and position ventilator grilles
➳ Brush grout
➳ Arrange for building control/warranty inspection
➳ Commence building superstructure
➳ Install templates for future windows and doors, etc.
➳ First lift of scaffolding required
Superstructure
➳ Bricklayers continue superstructure brickwork and blockwork, including work on any chimneys
➳ Install and bed lintels, including fireplace lintels
➳ Install flue liners as work proceeds
➳ Build in meter boxes for gas and electricity
➳ Electrician to install temporary consumer unit within electricity meter box
➳ Service suppliers to carry out their work to the boundary
➳ Plumber to reroute water supply to stopcock position
➳ Electricity providers to install meter and connect
➳ Second scaffolding lift required
➳ Arrange crane to lift first floor beams onto each bay and position (if required)
➳ Position the plasterboard batten clips
➳ Lay infill blocks ➳ Brush grout
Superstructure continued
➳ Continue building superstructure to wallplate
➳ Third and then fourth lift of scaffolding required
➳ Wallplate to be scarfed, bedded and tied down with proprietary wallplate straps
➳ Warranty inspection sometimes required
➳ Carpenters to build end trusses as templates
➳ Continue building up gable ends and chimney
➳ Additional lifts of scaffolding required at the gable ends
➳ Plumber to fit lead flashings, trays and skirts to chimney
➳ Plumber to install vent pipes and flashing skirts as they come through the roof
➳ Bricklayers to top out and fit chimney pot
➳ Bricklayers to point chimney flashings
Construct Roof
➳ Carpenters to sling roof trusses, and trusses to be fixed down to wallplate ➳ All binders and bracing to be fixed at node points
➳ Layboards to be fixed to valleys
➳ Dormers to be constructed at this point
➳ Fascia and soffit to be fixed together with any necessary ventilation grilles or strips
➳ Warranty inspection sometimes required
➳ Any roof tanks must be installed at this point
Roof Covering
➳ Roofers begin to cut and lay undercloaking to the verges
➳ Roofers to felt and batten
➳ Tiles/slates to be laid
➳ Ridge/hip tiles to be laid and bedded
➳ Valley tiles to be laid, or fibreglass or lead valleys to be laid
➳ Plumber to dress down flashings and skirtings
➳ Decorators to paint/stain fascias, soffits and barges
Exterior & Interior Fittings
➳ Plumbers to fix guttering
➳ Window suppliers to fit external joinery
➳ Plasterers to carry out any external rendering
➳ Scaffolding to come down
➳ Plumbers to fit downpipes and connect to drainage upstands/gullies
➳ External decoration
➳ Carpenters to commence first fix by fitting door linings, building any studwork partitioning and fixing window boards
➳ Carpenters to fix plasterboard noggins and box in vent pipes
➳ Plumber and carpenter to liaise with building of any necessary stands in roof
➳ Carpenter to fix loft trap
First Fix
➳ Plumbers to lay flooring membrane and insulation, taping all joints and sealing up to the damp-proof course
➳ Underfloor heating (UFH) loops to be laid and fixed
➳ All first fix plumbing for hot and cold and waste within floor zones to be laid
➳ Internal gas pipework installed
➳ UFH pipework to be brought to manifolds and outlet positions
➳ Supply and fix company to pump in and lay level floor screed and leave for three days
➳ Protective hardboard/ cardboard to be laid on screed
➳ Electrician to fix carcass wiring for lighting and power circuits together with all backplates
➳ Consumer unit/units to be positioned
➳ Wiring taken to external lighting points
➳ TV aerial/satellite cables to be installed to required positions
➳ Internal telephone wiring to be installed to required positions
➳ Home entertainment/ smart systems/alarms to be carcassed
Drainage & External
➳ Groundworkers to begin digging the trenches for drainage runs
➳ Trenches backfilled to 150mm with pea shingle ➳ Drains laid to required falls
➳ Brick/concrete section manholes constructed, or purpose-made manholes, rodding eyes and gullies set in runs
➳ Building inspector to approve laid drains
➳ Drains haunched over with pea shingle
➳ Drainage trenches backfilled
➳ Work to connect to main sewer in road to be carried out by approved contractors ➳ Carpenter to finish boxings and noggings ready for plasterer
➳ Groundworkers to commence driveways and pathways
➳ Bricklayer to build any fireplaces and hearths
➳ Gas meter to be installed and connected
➳ Plumbers and electricians to liaise on all cross bonding and earthing
ceilings/Drylining
➳ Main staircase to be fitted by the carpenter and protectively covered
➳ Dryliners/plasterers tack ceilings
➳ All external and blockwork walls lined with plasterboard on dots and dabs
➳ All studwork walls and pipe boxings tacked with plasterboard
➳ All joints and angles filled and scrim taped
➳ All abutments of differential materials jointed with mesh
➳ All joinery to be sealed internally and externally with mastic
➳ Dryliners/plasterers to skim coat all walls and ceilings
➳ Decorator to paint/ treat backs of all skirting and architraves
➳ All roofing insulation to be installed
Second Fix carpentry
➳ Carpenters hang internal doors
➳ Skirting and architrave to be fitted by carpenters
➳ Bottom tread of staircase to be fitted, balustrading and handrails to be fitted, as well as linen cupboard shelving
➳ Fit of loft door and ladder
➳ Timber floors to be laid by carpenters or specialists and protected
➳ Ceramic floor tiles to be laid by specialist tilers and protected
➳ Carpenters/specialist suppliers to fit/build built-in bedroom and bathroom furniture
➳ Kitchen units to be fitted
Second Fix
➳ All wiring connected to consumer unit
➳ Boiler to be positioned, plumbed and then wired in
➳ Sink units to be plumbed in, earthed and cross bonded
➳ All sanitaryware to be fitted and plumbed in
➳ Radiators and towel rails to be fitted and plumbed in
➳ Underfloor heating loops to be connected to manifolds
➳ Electrician to check cross bonding and earthing to all sanitaryware, sinks, radiators, etc.
➳ Boiler to be wired in; control systems and room thermostats to be wired in
➳ Plumber and electrician to attend firing up and commissioning of boiler
➳ All pipework and connections to be flushed through and pressure tested
➳ Central heating to be left on ‘test’
decorating
➳ Worktops, made from the previously taken templates, to be fitted
➳ House to be thoroughly cleaned with all debris and dust removed to outside
➳ Decorators to snag any holes, blemishes or rough patches on walls, making good
➳ Internal timber to be sanded smooth or rubbed down with wire wool
➳ Decorators to paint all walls and ceilings, mist plus two coats of emulsion
➳ Internal timber to be knotted, painted, primed, undercoated and top coat glazed, or internal timber to be two-coat stained
➳ Specialist tilers to fix ceramic wall tiles to kitchen and utility ➳ Baths to be filled, in order to settle, before tilers fix any wall/ splashback tiles ➳ Water meter to be installed
landscaping
➳ Groundworkers or landscape gardeners to level the ground and prepare ➳ Topsoil from storage to be placed where required, with extra shipped if necessary ➳ Site hut to be removed or re-sited if intended for use as a garden shed ➳ Secure site storage to be sold off or returned to hirers ➳ Groundworkers to complete driveway surface ➳ Patio slabs to be laid ➳ Bricklayers to build any required dwarf/ decorative walling ➳ Lawned areas to be levelled ready for seeding or turfed ➳ Approved contractors to complete any bellmouth and kerbing to road
completion
➳ Whole house to be thoroughly cleaned out
➳ All windows polished and all labels removed from glass and appliances
➳ All polystyrene packing to be removed from cookers
➳ All stabilising bolts to be removed from washing machines/driers
➳ Site toilet and any remaining plant on hire to be off-hired
➳ Readings to be taken on all meters
➳ Central heating switched to ‘run’
➳ Telephone company to connect
➳ Contractors to install TV aerials and/or satellite dishes
➳ All trades return to work through items on the snagging list
➳Carpets to be laid
➳ Local authority to be advised of completion to arrange for council tax valuation
➳ Energy Performance Certificate to be prepared and sent to building control
➳ Building control final inspection and issuing of Completion Certificate
➳ Warranty inspector’s final inspection and issuing of warranty
➳ Arrange protective covering for floor surfaces prior to delivery of furniture
➳ Switch self-build site insurance policy to homeowners’ policy H