project notes
Build timeline
House purchased Jun 2015 First planning application
submitted Mar 2016 Planning permission approved May 2016
Start on site Jun 2016
First fix Oct 2016
Second fix Dec 2016 Final decoration Dec 2016
Occupied Dec 2016
suppliers
Architect CandO Design: candodesign.co.uk Principal contractor KRM: krmcontractors.co.uk
Site preparation and finishing MSC Property: mscpropertyservices.co.uk Windows and external doors Spectrum Glazing: spectrumarchitectural.com MVHR system Zehnder: zehnder.co.uk
Bathroom porcelain tiles Lapicida: lapicida.com Flooring (upstairs and hallway) Karndean: karndean.com Downstairs porcelain tiles Minoli: minoli.co.uk Shower bases and enclosures Matki: matki.co.uk Bath, vessel basins and
wall-mounted brassware Victoria + Albert: vandabaths.com/en Composite worktops in kitchen and bathrooms Silestone: silestone.co.uk Kitchen appliances and sinks Smeg: smeguk.com Decorative radiators in bathrooms and kitchen radiator Bisque: bisque.co.uk Lighting Astro: astrolighting.com In-wall frames and ensuite in-wall shower Grohe: grohe.co.uk Boiling hot water kitchen tap Abode: abodedesigns.co.uk Ceiling speakers and in-wall wiring Armour Home Electronics: armourhome.co.uk
selected Build costs
Prelims (site set up, management fees,
erect scaffolding) £5,050
Windows and doors £26,000 Kitchen £19,000 Plumbing and
heating £17,000
Electrics £7,700
Carpentry/ joinery £3,100
Redecoration £3,500