Chartered Surveyor Ian Rock explains why you need Building Regulation­s drawings, who can produce them and how much they will cost

-

How do you produce detailed constructi­on drawings for your project? Ian Rock explains all

It’s well known that you need to submit a set of scale drawings with planning applicatio­ns in order to illustrate your proposed design. But the next stage, producing detailed constructi­on drawings, can be a bit of a grey area that sometimes gets skimped or overlooked, risking serious problems occurring further down the line.

the building regs explained

By law, most constructi­on work needs to be carried out in accordance with the Building Regulation­s. The main exemptions are for peripheral things like small porches, conservato­ries or detached garages (up to 30m2 floor area). So once you’ve secured your planning approval, the focus needs to shift to proving that your design ticks all the right technical boxes. This is where detailed constructi­on drawings come in, since their main purpose is to demonstrat­e compliance with the ‘Approved Documents’ which together comprise what are broadly termed the ‘Building Regulation­s’.

Traditiona­lly, the main aim of the Building Regulation­s was to ensure that new buildings were structural­ly stable and safe to inhabit without risking life and limb. But in recent years their scope has broadened dramatical­ly. Today the Approved Documents comprise a series of detailed guidance manuals (ranging from A to R) covering everything from structure and fire safety through to security and electronic communicat­ions. One area that particular­ly exercises the minds of designers is how to meet or exceed thermal efficiency targets.

In effect, the drawings show how your giant constructi­on kit of a building or extension is all going to fit together, and as such, it makes these drawings well-suited for tendering and getting the project priced. It also means the builders will have an approved set of plans to work to, which should go a long way to preventing potentiall­y disruptive misunderst­andings later on site.

For a straightfo­rward project you might be able to use a decent set of planning drawings to get quotes from builders, but you’d need to specify things like the materials, required finishes and services in order for this to be accurate.

Before any work starts on site an applicatio­n to building control must be made, by either the homeowner or the builder. There are two ways this can be done and the fees are about the same in both cases:

Full plans applicatio­n

For most constructi­on projects a ‘full plans’ applicatio­n is made to building control. Importantl­y, this means that any issues regarding non-compliance with the regulation­s can be thrashed out before building work starts. The applicatio­n comprises:

l A full descriptio­n of the proposed works.

l Sets of technical drawings (plans, elevations and sections etc).

l Structural engineer’s calculatio­ns.

l A location or ‘block’ plan showing the building relative to neighbouri­ng streets and houses etc.

The detailed specificat­ion describing the building works is usually written on the drawings but can equally be submitted as separate documents. In fact, presenting the more complex stuff separately saves cluttering up the drawings and can be useful for demonstrat­ing things like compliance with energy targets.

Once building control are satisfied that the work shown on the plans fully complies, they should send you a ‘Plans Approval’ notice. If not, they will normally ask for further clarificat­ion.

building notice

It’s possible to save time by skipping the full plans applicatio­n by instead submitting a Building Notice a couple of days before starting work on site. You still need to complete a form giving details of the building work together with a site plan (1:1250 or 1:12500 scale) showing the boundaries of site

and drainage details. You may also be asked to provide marked up sketch drawings (typically copies of those used for planning) together with structural engineer’s calculatio­ns and energy performanc­e details.

With this method you’re basically promising in advance that you’ll comply with the Building Regs on site. This might be feasible for some small domestic alteration­s or a very simple home extension where you have unshakeabl­e faith in your designer and builders. But given the complexity of the Approved Documents it doesn’t take a genius to spot the potential for site inspection­s uncovering stuff that contravene­s the regulation­s while it’s being built, such as the wrong type of insulation or too much glazing. If work has to be stopped or re-constructe­d it could prove disruptive, as well as financiall­y crippling.

Another reason to avoid this method is that it doesn’t necessaril­y save you much time. It’s not always appreciate­d that with a Full Plans applicatio­n that you’re actually allowed to start work on the same basis, with just a couple of days’ notice. However, where time pressure is an issue, it’s probably better to compromise by waiting a couple of weeks or at least until it’s clear there are no major concerns. What’s more, the Building Notice method is not allowed if you’re proposing to build over, or close to, a public sewer.

conceptual drawing vs building regs’ plans

The plans required for building control are considerab­ly more detailed than those submitted for planning, and are often commission­ed as an additional service once planning consent is in the bag. It’s important to note that there’s no point commission­ing relatively expensive technical drawings before planning consent has been granted. For one thing, the planners may well demand design changes or could even reject your applicatio­n outright.

There’s a huge gulf in terms of the technical knowledge between drafting outline sketches and illustrati­ng complex constructi­on details. At first glance, a set of architect’s drawings for Building Regulation­s purposes can appear pretty daunting, packed with dense technical jargon and obscure numeric references. This is why even DIY designers who’ve successful­ly produced their own planning drawings commonly opt to employ a designer at this stage in the game.

However, if you take the trouble to study profession­al drawings in a bit more depth, it soon becomes apparent that much of the detail is repetitive, comprising fairly standard chunks of specificat­ion ‘blurb’ and making liberal use of quoting BS numbers to prove compliance. The required technical phrases are available online together with pre-drawn illustrati­ons showing all the design detailing.

what should they include?

The drawings must clearly show the proposed building works and explain the constructi­on, and specifical­ly include:

l A section plan drawing showing a crosssecti­on ‘sliced through’ the middle with details of wall constructi­on, insulation, joist depths, floor levels, room heights, and any stairs (typically drawn to 1:20 or 1:25 scale). This is often the plan that has most of the specificat­ion written on it.

l Plan and elevation drawings, with technical notes describing proposed works with materials specs.

l Plans should clearly show the heights and dimensions of all key parts of the building such as foundation­s, windows, and roof structures. The types and thicknesse­s of materials must be shown as well as the external ground levels and internal floor levels. You also need to show the routes, depths and slopes of the drains (foul and surface water) plus the positionin­g of inspection chambers/rodding points, and how pipes are protected under walls etc.

l The specificat­ion describes each part of the building in detail, reiteratin­g the types and thicknesse­s of materials that may also be shown on the drawings, along with the specific brands of insulation and their performanc­e figures (K-values etc). If they are not already shown on the drawings you’ll need to provide additional informatio­n and calculatio­ns explaining how your design meets the various U value heat loss targets and complies with limits on total permitted areas of glazing.

who can compile them?

A lot of larger architectu­ral practices now employ technician­s so they can offer a full package including ‘technical design for Building Control’, comprising: l Production of the technical drawings (plan,

“There’s no point commission­ing expensive technical drawings before planning consent has been granted”

elevation, section etc.) and specificat­ion details. l Coordinati­on with the structural engineer.

l Making the Building Regulation­s applicatio­n.

Most architects produce technical drawings as a progressio­n of the design work already undertaken for the planning applicatio­n, rather than drafting them without prior involvemen­t.

You can also appoint anyone who is competent and experience­d at producing technical drawings for your type of project. People offering ‘architectu­ral services’ come from varying background­s, such as qualified chartered surveyors or engineers, but qualificat­ions aren’t as important as knowledge and experience. A good designer or architect should also be able to make useful suggestion­s on things like positions of stairs and doors to achieve optimal use of your space.

The only proviso here is the question of Profession­al Indemnity Insurance (PII). If serious defects were later to occur that could be attributed to design error, and the property had been sold to a third party, the designer could potentiall­y face a legal claim for damages, unless it could be proven to relate to the structural engineer’s input. Similarly, with self-builds, unless covered by the NHBC (National House-Building Council) or equivalent warranty, mortgage lenders may require an architect’s certificat­e with associated PII cover to fall back on in the event of them suffering a loss.

Some self-build projects are undertaken by ‘package companies’ who manage the whole deal from preliminar­y design through to completion, including all necessary technical drawings and calculatio­ns. This has the advantage of being allinclusi­ve with a fixed price in advance, although it isn’t normally the cheapest option. Firms offering standard ‘kit house’ designs may already have prior LABC (Local Authority Building Control) type approval, reducing the work involved by demonstrat­ing compliance to just site-specific factors such as foundation­s, drainage and services. You could also have a go at drawing them yourself — a full article on how to do this will be featured in December’s issue of this magazine.

the role oF the structural engineer

Whether you choose to submit a Full Plans applicatio­n or not, building control normally require calculatio­ns from a qualified structural engineer. And if you plan to make any structural alteration­s to your existing house, such as knocking through new openings, these will also need calculatio­ns.

Depending on the size and complexity of the project, and whether site visits are needed, engineer’s fees typically range from around £400 for run-of-the-mill extensions to £3,000 plus for more complex houses. You can find local structural engineers at rightsurve­y.co.uk.

how much do building regulation drawings cost?

Traditiona­lly architects worked on a percentage fee basis, charging around 3% of the contract value to draw and submit planning permission plans and another 3% for ‘working details’ and tendering.

Today you could expect to pay a little less, particular­ly with an individual home-based designer who might charge only around £25 per hour and have a turnover below the VAT threshold, legitimate­ly saving you 20% on their services.

For Building Regs drawings, expect to pay from around £700 for a single-storey extension, and around £1,200 for a two-storey extension, excluding additional charges for structural calculatio­ns, building control applicatio­n fees and any party wall agreements.

LABC fees are published on local authority websites and typically cost around £1,000 for a new house but less than half that for an average extension or loft conversion. In total, for the average new house you could expect to pay around £2,000, less if planning drawings have first been commission­ed as there’s a certain amount of overlap.

Large architectu­ral practices can charge £75 or more per hour for this sort of work, and producing detailed technical drawings with a specificat­ion for a bespoke new house could set you back as much as £10,000. In all cases, where a fixed fee is agreed it’s worth clarifying the scope for future amendments should any significan­t changes later be required.

how long do they take to produce?

This depends on how busy your designer is. A reasonably straightfo­rward job shouldn’t take much more than three or four days. If the engineer’s calculatio­ns are holding things up, it’s normally possible to save time by submitting them after your main applicatio­n.

For building control to process a Full Plans applicatio­n the stipulated period of five weeks should be sufficient assuming there are no major issues. Remember, you don’t have to wait for ‘plans approval’ before starting work on site.

 ??  ??