PREPPING THE FLOOR FOR LVF

-

“To prep a timber or concrete subfloor for LVF, the surface must be cleaned and all dust, dirt and debris removed. For timber subfloors place 6, 9, 12 or 18mm plyboard on top — the size chosen will depend on the condition of the existing floor with thicker versions applied onto more uneven surfaces. Following installati­on of the plyboard, a primer coat is applied on top using a roller or paint brush.

“For a concrete subfloor, a latex floor screed (such as Instarmac Ultrafloor) can be poured on top. It takes a few hours until it’s touch dry.you must wait at least 12 hours before applying your chosen LVF. Prepping and installing the floor will cost between £75-125/m2 depending on the condition and more if floorboard­s need to be replaced or the concrete needs repairs,” advises Steve Corbyn of Sentinel Design and Build.