BUYING LAND WITHOUT PERMISSIONS: THE 10-STAGE PLOT-BUYING PROCESS
1. Establish your budget - 1 to 2 weeks
Work out how much you can afford to spend
Double check your numbers. Is there asnything you’ve forgotten?
Have a self-build mortgage broker review your plan
2. Appraise the plot - 2 to 4 weeks
Make sure the plot will support a project you want to build
Carry out a plot appraisal
3. Assemble your support team - 2 to 4 weeks
Identify any specialists you might need
Ensure you have the necessary expertise
4. Prove your plot’s planning potential - 4 to 6 weeks
Develop design concepts and get a planning appraisal
Hold a pre-app meeting with the council if necessary
5. Establish value of the plot - 2 to 4 weeks
Work out a fair plot price that reflects the expected costs of development. Don’t take the estate agent’s word for the price of the plot
6. Secure an option to purchase - 6 to 8 weeks
Negotiate a purchase price with the landowner
Instruct your legal team to agree the options terms
7. Instruct your team - 1 to 2 weeks
Make sure your team understands your needs and budget
Make sure the fees are affordable, even if things fall through
8. Prepare the submission - 8 to 12 weeks
Prepare a design in line with your brief, and check costs
Submit all required information to your LPA, including any surveys
9. Planning approval - 8 weeks to 12 months
Obtain confirmation of your LPA’S receipt of your application
Monitor the progress of the application
Respond and adapt to any concerns raised by the planning officer
Appeal within six months if refused
10. Complete the purchase - 8 to 12 weeks
Instruct your conveyancing solicitor to proceed
On completion, secure the site boundaries and get all the necessary insurance put in place