Ideal Home (UK)

THE BUILD IN PICTURES

Works started in January 2020 and finished in December. It cost around £530,000.

-

Demolition of the existing property got underway. Susie had considered an eco retrofit, but decided to go for a zero-vat-rated new build as they’d be able to incorporat­e more of what they wanted in their home.

The site was cleared and ready for the foundation­s to be dug. This meant the views of the surroundin­g hills were opened up – something the existing property was not taking advantage of.

The ground floor was constructe­d. The build used a typical cavity wall constructi­on method with beam and block suspended floor that is fully insulated. Trenches were dug out for the perimeter blockwork.

 ?? ??
 ?? ??
 ?? ??