Rail Express

LU WORLD

Already running late, the coronaviru­s outbreak looks set to further delay the long-planned upgrade work.

-

Slow progress on 1992 Stock overhaul.

KNOWN as the Central Line Improvemen­t Programme, the life extension overhaul project for the 1992 Tube Stock (used by the Central and Waterloo & City Lines) commenced back in December 2015. Its aim is to achieve compliance for the 25-year-old trains with the Rail Vehicle Accessibil­ity Regulation­s 2010.

Two cars were sent to Bombardier’s works at Derby in December 2018 so prototype designs could be developed. These cars, Driving Motor No. 91111 and Non-Driving Motor No. 92111, were later joined by Nos. 92446 and 93446 midway through 2019 to enable design work to progress on each of the four car types that make up the fleet.

The trains were built by British

Rail Engineerin­g Limited from the summer of 1990 onwards, and utilised a combinatio­n of early microproce­ssor systems along with establishe­d electro-magnetic systems. This means that the Central Line trains are in effect hybrids, using a combinatio­n of modern and older control systems that has not led to a happy merger of technologi­es.

The original bogies have already been replaced, as have around half of the car ends due to common water ingress issues as part of a previous overhaul programme. The CLIP life extension work will include: fitting AC motors to the bogies; installing new passenger informatio­n systems and LED saloon lighting; removing seats to make space for wheelchair use; and replacing the door interlocki­ng system. Some details still need to be clarified, such as the height for perch seats, a RVAR-compliant floor covering, and the final interior decoration.

WORKSHOP DELAY

Delays to the completion of other projects, such as the Track Maintenanc­e Unit Workshop, has hindered progress on the facilities being built at Acton Depot to undertake the 1992 Stock overhaul work.

Constructi­on began in early 2018, but the building is nowwaterti­ght and concrete pouring for the pit-roads was almost complete by the end of 2019.

Whilst the fit out of the workshop with mechanical and electrical systems was progressin­g, the original intended target to accept the first unit ready for overhaul in April 2019 has long passed. Consequent­ly, it has been decided that trains one, two and three will now be overhauled at Derby.

Prior to the coronaviru­s outbreak, the reschedule­d target for the first unit to enter the newworksho­p had already slipped back to January 2021. With all project and constructi­on work across Transport for London nowhalted, it may not be until mid to late-2021 before any train enters the newshed for overhaul.

Newspapers in English

Newspapers from United Kingdom