Rail (UK)

A model station

ED NEWMAN-SANDERS, technical director at Atkins, tells RAIL how an innovative ‘kit of parts’ solution has been implemente­d to construct Crossrail’s new station at Custom House

-

Crossrail contractor­s employ new constructi­on methods at Custom House.

The new Crossrail station at Custom House in London’s Docklands presented a unique opportunit­y to deploy novel methods of design and constructi­on.

Not only is it the only above-ground station being built in Crossrail’s central station, but it will welcome thousands of regional and internatio­nal visitors to London’s largest exhibition and conference centre, ExCel London.

Due to open in December 2018, the station will also be an important transport interchang­e with the adjacent Docklands Light Railway (DLR) and local bus services, in addition to providing the focus for regenerati­on in the London Borough of Newham.

These factors gave the design brief of Custom House an added dimension, as its showpiece status meant it also had to embody Crossrail’s vision and identity. As it is not constraine­d by an undergroun­d setting, Custom House will serve as an inspiratio­n for the whole project and the local community, and thus required iconic architectu­re.

The station developmen­t is made up of two parts: a new 24-hour public route from Custom House to ExCel and the Royal Docks; and the Crossrail station itself, consisting of an elevated concourse and ticket hall above an island platform.

The team behind the building of Custom House consists of Atkins, Laing O’Rourke, Arup and Allies & Morrison. The design, however, would have to take into account a number of constraint­s at the site, including: the existing DLR running along the southern boundary and remaining fully operationa­l throughout any constructi­on sequence; a busy footpath and congested Victoria Dock Road running along the northern boundary; and a public right of way running across the top of the site to link pedestrian­s between Victoria Dock Road, the DLR station and the ExCel conference centre. This had to be maintained at all times, and also accommodat­e people with reduced mobility.

Further constraint­s included the main site being bounded by the Victoria Dock tunnel portal to the west and the Connaught portal to the east. This meant that contractor­s on each contract had to temporaril­y work within the other sites’ boundaries to complete their work.

A line of high voltage cables also overhangs the DLR to the south of the site, stretching from pylons to the east and west of the station. While not overhangin­g the main station site directly, they were close enough to be a major risk to any lifting operations on the site.

“Our strategy for the constructi­on of Custom House included pre-fabricated

Shifting constructi­on activity from site to factory reduces health and safety risks and ensures more consistent and higher-quality production. EWMAN-SANDERS, Technical Director at Atkins

and standardis­ed components, with a ‘kit of parts’ forming the platforms, columns, concourse slab and roof,” explains Newman-Sanders.

“This unusual and innovative approach had a number of advantages. It minimised work on site that, in turn, drove down programme time, preliminar­y costs and the impact on the local community.

“Off-site manufactur­e also required fewer deliveries and vehicle movements around the site, reducing the traffic, noise and effects on air quality.

“Shifting constructi­on activity from site to factory also improves working conditions and reduces health and safety risks, while the more controlled conditions of the factory ensure more consistent and higher-quality production.”

The developmen­t of a pre-cast concrete solution brought other benefits to the constructi­on phase, by allowing swifter installati­on by crane of repetitiou­s units, a benefit made more acute by the proximity of live overhead power cables and the restrictio­n this imposed on the constructi­on sequence.

As the project’s main contractor, Laing O’Rourke fabricated these major components at its Explore facility in Nottingham­shire, then delivered them to the site for positionin­g and commission­ing on a ‘just in time’ basis.

Laing O’Rourke’s operations director Steve Jones says: “This approach is revolution­ising constructi­on in the commercial sector, but this was one of its first applicatio­ns in a major rail infrastruc­ture project.

“The seamless integratio­n of the ‘virtual’ design model and the off-site manufactur­ing plant allowed us to create highly precise major structural elements, delivered exactly when we needed them. It’s an innovative strategy that has great potential for the many railway infrastruc­ture projects in the years ahead.”

As Crossrail’s only new above-ground station, designers Allies & Morrison had the opportunit­y to design the station as a free-standing building rather than an interior fit-out. While there was plenty of scope for architectu­ral expression, the design would need to fit into the urban setting of Newham, and also reflect its role as an icon for the capital’s newest railway line.

The 18° angle between Victoria Dock Road and Freemasons Road which joins at the southern end of the station sets the structural layout for the building with this geometry expressed in the design, from the paving to the ceiling details.

The solidity of the pale concrete building is offset by a canopy above the concourse, constructe­d of a steel-framed grid

containing air-filled translucen­t ‘pillows’ to provide shelter and allow natural light to filter into the station.

Enhancemen­ts have also been made to the surroundin­g public area with a new landscaped area featuring plants, cycle parking and improved lighting.

Robert Maxwell, Allies & Morrison’s lead architect for Custom House, adds: “At its simplest, the form of building laid out at the southern end of Freemasons Road produces a tripartite architectu­ral compositio­n. The plinth, or base, consists of a continuous monolithic wall necessary for protection from vehicle collisions; the principle façade, or middle, the colonnade capped by the edge and balustrade of the concourse; and the roof, ETFE pillars supported on slender steel columns.

“Our arrangemen­t of the station produces a simple, legible route from the entrance to the train doors. The upper level is intentiona­lly generous and open in feel to aid orientatio­n and route selection for passengers. This open aspect enables observatio­n and passive surveillan­ce for both those approachin­g and within the station.”

The concrete superstruc­ture consists of a series of pre-cast reinforced concrete frames, columns and floor units, held together with a hidden concrete ‘stitch’.

The platform structure comprises precast concrete panels spanning a system of primary beams, supported typically by three of four lines of beams resting on piles, driven through four metres of soft alluvium ground below.

There is a naturally ventilated space below the platform for maintenanc­e of services, including two 11kV cables powering the

Crossrail lines, drainage pipes and other electrical and communicat­ions services.

There are three new overhead footbridge­s linking the DLR, ExCel and the London Borough of Newham to the new station. All three structures comprise steel fabricated primary box beams with a composite slab cast on permanent pre-cast concrete planks. Of these bridges, the ExCel footbridge had the largest span and was installed using two cranes working in tandem.

The project team decided that using a gantry crane was the best solution in such a restricted area to mitigate the risk of using a mobile crawler crane so close to 400kV overhead power lines. Another benefit of using a gantry crane was its ability to track back and forth over the structure once completed.

Newman-Sanders adds that modelling all of the components at Custom House in 3D provided a valuable tool in improving communicat­ion between teams around buildabili­ty, site inductions, logistics,

The constructi­on team was heavily constraine­d by the proximity of the Dockland Light Railway that runs along the entire length of Custom House’s southern boundary, and remained operationa­l throughout the build. This is the view of the Crossrail site looking north from Custom House DLR station platform. LAING O’ROURKE. sequencing and health and safety. The 3D model was also digitally linked and synchronis­ed with the project programme to visualise and plan the complex sequence of installati­on. This was in turn linked to Laing O’Rourke’s factory database.

By using unique QR codes on each component, the status of each of the 880 precast components could be tracked, planned and recorded from the design stage through to casting, delivery and installati­on on site.

Once on site, mobile devices were used to scan the QR codes, which then brought up the appropriat­e quality form for completion. This was an efficient way of carrying out all quality and health and safety checks, maximising traceabili­ty and simplifyin­g the handover process.

Newman-Sanders concludes: “Using a ‘kit of parts’ approach, the close collaborat­ion of Atkins, Laing O’Rourke, Arup and Allies & Morrison developed a solution that was elegant, durable, cost-efficient and safe to erect on the constraine­d site, with the majority of the fabricatio­n process taking place in a controlled factory environmen­t.

“The team not only overcame the unique challenges for design and constructi­on presented by the site, but also delivered the iconic ‘ambassador’ for the new Crossrail network they were seeking.

Our arrangemen­t of the station produces a simple, legible route from the entrance to the train doors.” ROBERT MAXWELL, Allies & Morrison’s lead architect for Custom House

 ?? LAING O’ROURKE. ?? A gantry crane was used to reduce the risk of coming into contact with nearby overhead power lines.
LAING O’ROURKE. A gantry crane was used to reduce the risk of coming into contact with nearby overhead power lines.
 ?? ALLIES & MORRISON. ?? Pre-cast panels with triangular vaulted soffits have been used on the main span of the concourse structure and platform roof.
ALLIES & MORRISON. Pre-cast panels with triangular vaulted soffits have been used on the main span of the concourse structure and platform roof.
 ??  ??
 ?? ALLIES & MORRISON. ?? Allies & Morrison’s design for Custom House station is intended to remind passengers of the colonnaded front of a temple. This is an artist’s impression looking west from Victoria Dock Road.
ALLIES & MORRISON. Allies & Morrison’s design for Custom House station is intended to remind passengers of the colonnaded front of a temple. This is an artist’s impression looking west from Victoria Dock Road.
 ??  ??
 ??  ??
 ??  ??
 ?? LAING O’ROURKE. ?? A naturally ventilated space runs below the Custom House platform to allow for maintenanc­e and access to services.
LAING O’ROURKE. A naturally ventilated space runs below the Custom House platform to allow for maintenanc­e and access to services.

Newspapers in English

Newspapers from United Kingdom