Rail (UK)

Banbury in transition

PAUL STEPHEN reports on how a team of more than 300 staff and subcontrac­tors from Siemens Rail Automation commission­ed the final stage of the Banbury Resignalli­ng Programme, on budget and to schedule

-

Siemens Rail Automation and Network Rail complete Banbury Resignalli­ng Programme in unison

Until only a few weeks ago, Banbury station was an unusual location for signalling. Although its two main lines were fully signalled using modern multiple aspect coloured light signals, its bay platforms and goods loop retained semaphores, controlled by two Great Western Railway-era mechanical signal boxes.

All that has now changed following a nine-day blockade, during which all signalling equipment on a 22-mile stretch of the Chiltern Main Line was upgraded to Siemens’ Trackguard Westlock computerba­sed interlocki­ng system.

Between July 30 and August 7, Siemens and Network Rail worked jointly to decommissi­on life-expired equipment from just north of Leamington Spa to Anynho Junction and Heyford in the south – and at all stations between Banbury and Heyford.

Control of the signalling previously operated by Banbury North and Banbury South signal boxes has now been transferre­d to a single desk at West Midlands Signalling Centre in Birmingham, as have the remaining functions of Leamington Spa Signalling Centre.

Banbury South Signal Box – built in 1908 – has now been demolished, while Banbury North Signal Box – built in 1901 – will share the same fate shortly after a number of 90-minute pre-booked guided tours have been completed on October 2.

The project involved 18 months’ initial design work, and aims to enable much improved headways via more than 50 newly installed LED signals. These are more reliable, energy efficient and require far less maintenanc­e than the equipment they replace.

In addition, train protection warning system (TPWS) and axle-based track circuit blocks have been installed to provide continuous train detection throughout the re-signalled area, including Banbury’s sidings and loops.

The track layout has been rationalis­ed through Banbury station and a connection laid to Chiltern Railways’ new depot at its southern end, which is set to open next year. Four sidings are being built there to stable up to 18 trains overnight.

Finally, a fourth platform has been constructe­d at Banbury to increase capacity A significan­t amount of work had already

taken place during planned closures on Sundays throughout 2015, and possession­s on both Christmas Day and Boxing Day.

All this amounted to £ 76 million-worth of work being completed following the most recent blockade, and resulted in 24 new points being installed, 50,000 tonnes of ballast laid, along with 14,000 metres of new rail and 11,200 new concrete sleepers.

Elgan Davies, Network Rail’s Programme Manager, said that the project had been a great example of collaborat­ion between a number of Network Rail’s key suppliers. He added: “Everyone worked with a single purpose to finish this challengin­g programme of work on time and in a safe manner. From concept to commission­ing, this project has been a textbook example of how it should be done.”

Siemens’ Project Manager Stuart Hamilton said. "The combined Network Rail and Siemens team worked extremely well across all discipline­s throughout the project, with great working relationsh­ips and a wonderful team spirit. The project also provided fantastic personal developmen­tal and experienti­al opportunit­ies for many of the team members, which were eagerly taken.

“This programme was managed to enable

From concept to commission­ing, this project has been a textbook example of how it should be done. Elgan Davies,

a safe, timely and successful delivery, culminatin­g in a smooth commission­ing at the end of the blockade.”

Dave Penney, managing director at Chiltern Railways added: “The work at Banbury was an essential investment in the long-term reliabilit­y of the railway and was successful­ly delivered on time. Through a modernisat­ion of the signalling system, Chiltern Railways services can remain some of the most punctual in the country. The 18-month project is now complete, and I would like to thank all of our customers who have shown patience and understand­ing during the improvemen­ts, particular­ly during the recent nine-day line closure between Leamington Spa and Bicester.”

Flood alleviatio­n work was also completed at the same time just over 30 miles to the south, at Hinksey in Oxfordshir­e, where the track level was heightened between July 30\

 ?? SIEMENS. ?? Siemens Rail Automation was awarded the £40m contract in January 2015 to renew signalling around Banbury and transfer control to West Midlands Signalling Centre in Birmingham.
SIEMENS. Siemens Rail Automation was awarded the £40m contract in January 2015 to renew signalling around Banbury and transfer control to West Midlands Signalling Centre in Birmingham.
 ?? SIEMENS. ?? The railway between Banbury, Bicester and Leamington Spa re-opened on August 8 after a nine-day blockade to complete a £76m upgrade of the Chiltern Main Line.
SIEMENS. The railway between Banbury, Bicester and Leamington Spa re-opened on August 8 after a nine-day blockade to complete a £76m upgrade of the Chiltern Main Line.

Newspapers in English

Newspapers from United Kingdom