Rail (UK)

Foreign legion

RICHARD CLINNICK travels to Morocco to discover how Colas Rail is building Africa’s first high-speed line

- RAIL photograph­y: RICHARD CLINNICK

While HS2 has received Royal Assent, in Morocco the country’s first long-distance high-speed line is nearing completion.

There are many similariti­es between High Speed 2, which was given Royal Assent in the UK on February 23 ( RAIL 822), and the historic highspeed line being constructe­d in Morocco.

Both are deemed vital to the economies of their respective countries. And both will free up capacity on existing ‘classic’ lines, to enable more local journeys and long-distance freight to operate.

In the North African country, Colas Rail is using expertise gained from high-speed projects it has worked on across the globe to build the first long-distance high-speed line in Africa.

The $ 2 billion (£1.6bn) project has been in developmen­t for many years, with the Moroccan government expecting the railway to deliver wealth via improved business links. The railway will slash journey times from Tangier to the capital Rabat from around 4hrs to 47 minutes.

Much like in the UK, this is merely Phase 1 of a much larger project involving more high-speed lines. This means that the trains being built will operate on both the brand new infrastruc­ture and the ‘classic’ network, until such time as the next phase is open. Eventually trains will serve other North African countries - the ambition is that, one day, the region’s HS network will link with Europe and the Middle East.

Morocco has been investing in transport infrastruc­ture for many years. Roads often run parallel to an electrifie­d railway, serving towns where new-build developmen­ts are springing up, attracting new businesses to the country.

A principal reason for the developmen­t of the country’s infrastruc­ture is the inaugurati­on of the port of Tanger-Med, one of the largest container hubs in the Mediterran­ean.

To ensure continued developmen­t of the national transporta­tion system, Morocco decided to advance with a high-speed rail option - using proven technologi­es, albeit in an innovative way.

A new two-track system dedicated to highspeed trains is under constructi­on. It is 185 kilometres (115 miles) long, and will have a maximum speed of 320 kilometres per hour (200mph). The line will run (initially) from Tangiers in the north to Kenitra, which forms part of an administra­tive region with the cities of Salé and the capital Rabat.

Work for the high-speed line includes building the railway, erecting the overhead line catenary and signalling, and installing the power and telecommun­ications system. Additional­ly, work is required to adapt and improve the classic railway at Tangier and Kenitra stations, which will act as the termini for the first phase of the country’s HS route.

Logistics centres have been built at Sidi El Yamani (which housed 800,000 tonnes of ballast during RAIL’s visit) and Kenitra (the larger of the two sites). These will link to the classic railway to enable the delivery of constructi­on material.

Constructi­on has been split into north and south sections, each with four contracts. The combined eight contracts are named TORAC (Earthwork, civil engineerin­g structure and road reinstatem­ent). Additional­ly, there are separate contracts for the viaducts.

Colas Rail is the main contractor for the project, delivering the railway, catenary and work bases ( VCBT). The company’s Colas Rail Maroc is working with Egis Rail - the

This is merely Phase 1 of a much larger project involving more high-speed lines. This means that the trains being built will operate on both the brand new infrastruc­ture and the ‘classic’ network, until such as time as the next phase is open.

latter is responsibl­e for project management, administra­tion of testing and commission­ing, while Colas Rail Maroc carries out the constructi­on, commercial representa­tion and project administra­tion.

The relationsh­ip between Egis and Colas is strong in the UK, with both companies are working on the £1.2 billion Midland Metro Alliance.

Project Director Pierre-Gilles Douriez joined the project when it began in 2013. He tells

RAIL that Morocco has been investing in its infrastruc­ture “for years”, and that the highspeed line “is the final bit”.

He also confirms it is the first long-distance HS line on the continent, apart from one small section in South Africa. And although it may only be 115 miles long (the same distance as Norwich to London Liverpool Street), major difference­s in the geography present plenty of challenges. “The northern part is mainly hills, while the southern phase is flat,” he says.

Douriez explains that the contract includes delivery of the two work centres; constructi­on of the railway and overhead line equipment (OLE), including the supply of all related equipment for OLE; managing the work bases and global logistics; management of the railway security and work trains along the new line; insurance of security for the line’s access during constructi­on and commission­ing; testing and commission­ing of railway equipment; static and dynamic systems integratio­n; managing the contractin­g authority to supply contracts for railway equipment; and designing and building three long-rail welded vehicles (324 metres long).

Sleepers are constructe­d in Kenitra, as is all the OLE for the railway. There are five main workshops at that site, and all the components are referenced by SNCF - the Moroccan

authoritie­s chose to use proven technology, and looked to France and its successful HS operations. Equipment is also supplied from other European countries, including Spain, the Czech Republic and Belgium.

From Kenitra, the engineerin­g trains run along the already-built sections of the railway. The first one leaves at 0200, and by 0600 is on site 60km away. The maximum speed on the line is a slow 30kph.

In terms of operation, the standards are the same as the UK. There are three colours for the various work - green for daytime working, red for night-time working and blue for a long (distance-wise) worksite. Each site requires permission to access, with control at Kenitra. In total, there are 85 staff working on 25 trains per day on the line.

Douriez says that on the current railway system, journeys between Kenitra and Tangiers are lengthy: “It is one track on the classic line. It goes east then north. I have never met someone who does it in 3 hours 15 minutes, usually it is four hours.”

He says the project is vital because “there was no important city to city route”. Furthermor­e, he understand­s that when the

Moroccan HS line opens, freight will operate on the longer route, but will then be able to serve other ports, thus opening up new business opportunit­ies. Constructi­on of the HS line therefore serves as more than just a piece of infrastruc­ture to improve point-to-point journey times. There are no stations on this first phase of the line.

Colas must meet eight key deadlines in the project and, so far, it has met them all. On September 2 2013 it was awarded the VCBT contract; on June 1 2014 there was acceptance of works at the Kenitra work base, and on January 31 2015 work began on ballast deliveries and rail storage.

By December 2 2015 the high-speed line work order was confirmed, with a commitment for 1,000 metres of high-speed line built per day. By October 1 2016 there had to be 40% of the project completed (around 50km).

Testing and commission­ing began, as planned, in February this year. The next deadline is October, when the constructi­on work finishes ahead of the start of technical service and VCBT works acceptance.

The contractin­g authority is ONCF (National Office of Railways), and the contractin­g authority support is provided by SNCF Internatio­nal. Douriez is the legal representa­tive for Colas Rail as the Project Director, and a steering committee is

in place with three members from the contractor­s (one each).

At the workbases, different tasks are under way. The Kenitra site (about 70 hectares in size) was created under customer request, and is currently dedicated to the HS project. It also acts as a training centre. Staff are trained in specific duties relating to the constructi­on of the railway, including the operation of constructi­on trains, worker safety and security.

A model railway is housed in one of the

buildings. While not a 100% replica of the HS route, it helps in teaching the processes required in the constructi­on and operation, and is used to mimic the line. Currently it is being used for the engineerin­g trains and their various movements, but in time test trains and HS running will be taught using this method.

The site uses both French and Arabic languages (as per most of Morocco), while radio communicat­ions are all in French.

Training at Kenitra also involves theory sessions on railway and hygiene safety, with practical sessions. At the time of RAIL’s visit, 1,393 workers had been trained (1,147 in railway safety and 246 in hygiene and safety). This had been achieved through 258 sessions, including 231 railway safety sessions.

What’s fascinatin­g about this railway is that Colas is constructi­ng it first as a road, before then carrying out railway works.

Initial work includes topography and siting of OLE posts. Then the road constructi­on work begins. This involves excavation so that the catenary posts can be installed alongside the railway, which at this point continues to resemble a road rather than a multi-billionpou­nd railway. Once the masts are in place, the feeder wires are unreeled and strung between the masts (using road transport).

Next, the sleepers are sited along the railway before pre-ballasting takes place. This enables 30% of this particular part of the project to be completed in one go.

By constructi­ng the railway in this manner, Colas Rail is able to let the land settle and (in effect) lay the railway on the road, having already dealt with issues such as drainage and the land subsiding.

When it comes to the railway works, the sleepers are laid on the pre-ballast before continuous­ly welded rail is brought to the site. Douriez explains that the record for laying track is 3,564 metres in one eight-hour shift.

At the same time the OLE is also brought to the site. Then ballasting is carried out. This is delivered to site by rail, with materials arriving from the logistic bases. Once the ballast is laid, heavy mechanical packing takes place using various regulators from Colas’ fleet.

Stress relief of the track is the next task, followed by OLE erection (typically around 1.2km per shift). It is the OLE installati­on that Douriez says tends to slow down the teams - usually around 2,000 metres of track is laid per shift. Once completed, testing begins.

Trains operating on the new HS railway will be classic compatible vehicles, although Douriez says that by 2035 the authoritie­s want an entire HS network. The classic network in Morocco is 3,000V OLE, which means the trains must be dual-voltage.

Phase 2 of the scheme is planned to be the 50km from Kenitra into Rabat. Although not the largest city in Morocco, it is the administra­tive hub and needs that fast link to the increasing­ly industrial­ised northern ports.

Colas is everywhere in Morocco, building both roads and railways. Through its parent company it has been involved in HS constructi­on around the world, and the company believes the success and innovation developed for this historic project could be put to good use in Britain when the HS2 contracts are let. Certainly, the Moroccan experience presents an excellent case.

A model railway is housed in one of the buildings. While not a 100% replica of the HS route, it helps in teaching the processes required in the constructi­on and operation, and is used to mimic the line.

 ??  ?? The compound at Kenitra. Trains used for the constructi­on process start their journeys onto the new railway here. This is one of two sites used for this work. Overhead wires are being erected at Kenitra, in this view looking north. This was the...
The compound at Kenitra. Trains used for the constructi­on process start their journeys onto the new railway here. This is one of two sites used for this work. Overhead wires are being erected at Kenitra, in this view looking north. This was the...
 ??  ?? Colas Rail Executive Developmen­t Director Iain Anderson, next to El Hachef viaduct. While the OLE masts had been installed on the structure when RAIL visited, the tracks had yet to be laid. Travelling along the HS line southbound. Because no lineside...
Colas Rail Executive Developmen­t Director Iain Anderson, next to El Hachef viaduct. While the OLE masts had been installed on the structure when RAIL visited, the tracks had yet to be laid. Travelling along the HS line southbound. Because no lineside...
 ??  ?? The inspection train travelled on by RAIL. The locomotive was imported from Belgium.
The inspection train travelled on by RAIL. The locomotive was imported from Belgium.
 ??  ?? 1. A copy of RAIL at El Hachef viaduct, which is the longest structure on the new high-speed line. 2. The high-speed line is built initially as a road, after which the overhead catenary masts are erected. This view near Larache shows the line looking...
1. A copy of RAIL at El Hachef viaduct, which is the longest structure on the new high-speed line. 2. The high-speed line is built initially as a road, after which the overhead catenary masts are erected. This view near Larache shows the line looking...
 ??  ??
 ??  ?? Taken from an overbridge looking north at Sahel, near Kenitra, this view shows the gradients that feature in this area of the high-speed railway.
Taken from an overbridge looking north at Sahel, near Kenitra, this view shows the gradients that feature in this area of the high-speed railway.
 ??  ??
 ??  ??
 ??  ??
 ??  ??
 ??  ??
 ??  ??

Newspapers in English

Newspapers from United Kingdom