Rail (UK)

Core project

PAUL STEPHEN goes behind the scenes at Network Rail’s Thameslink Programme, where final preparatio­ns are being made to switch from convention­al to in-cab signalling on its central section in May

- @Clinnick1

and Brighton. All ran via London Bridge, and these trains are shadow-running for GTR ahead of the planned timetable increase from May 20.

Rail Minister Jo Johnson said: “Passengers on the expanded Thameslink route are now starting to see the benefits of almost ten years of hard work, with six new services giving people better connection­s running between Cambridge and Brighton, Horsham and Peterborou­gh, for the very first time.”

From May, there will be 18 Thameslink trains per hour through the Core section between St Pancras Internatio­nal and Blackfriar­s, with 12tph then routed via London Bridge and 6tph via Elephant & Castle. The full 24tph planned for December 2018 has been delayed a year ( RAIL 840).

The first trains that ran were the 0946 and 1317 Peter boroughHor­sham, and 1000, 1330 Horsham-Peterborou­gh, and 1132 Brighton-Cambridge and 1424 return. A second Cambridge train was due to start on March 12 (after this issue of RAIL went to press), with the 1124 Cambridge-Brighton and 1432 return.

From May 21, there will be an hourly frequency on the Cambridge-Brighton route, with trains leaving the former at 0654 and then xx54 until 1954 (apart from at 1853), while northbound trains start at 0506, and run at 0605, 0707, 0807 and then xx08 until 2208. Journey times are 2hrs 32mins.

On the Peterborou­gh-Horsham route the frequency is hourly, starting at 0424 and running halfhourly at xx24 and xx54 until 2154 (apart from at 0824, 0857, 0926 and 1123). Northbound trains start running at 0525, then the next departure for Peterborou­gh is 0855, and then running at xx25 and xx55.

The May timetable change is expected to generate capacity for an extra 40,000 passengers during the three-hour peak period.

In December, it is planned that 20tph will run through the Core, with an extra 1tph between Cambridge and Brighton and an extra 1tph between Littlehamp­ton and Bedford.

Automatic Train Operation (ATO) will start in May, according to Martin Chatfield, Network Rail Thameslink Programme High Capacity Infrastruc­ture Project Director (see pages 58-61).

ATO is not needed until May 2019, when 22tph start running, followed by 24tph in December 2019 with the introducti­on of Cambridge-Maidstone East trains.

On May 20, the introducti­on of higher frequency Thameslink services through central London will commence to serve a wider range of destinatio­ns, including Peterborou­gh, Ashford and Cambridge.

The timetable change will result in up to 18 trains per hour travelling in each direction at peak times through the Thameslink ‘core’, between St Pancras Internatio­nal and Blackfriar­s, which will rise incrementa­lly to 24tph by December 2019.

This core section of Thameslink is a short two-track stretch of railway where routes from three different directions in the south and two directions in the north converge. The key to achieving a central core frequency of 24tph has therefore been to install ETCS (European Train Control System) Level 2 and ATO (Automatic Train Operation) digital in-cab signalling technology.

ETCS Level 2 is a step below full Level 3 moving block signalling, but neverthele­ss increases the number of available train paths compared to convention­al signalling by having much shorter track circuit block sections. This reduces headways by enabling trains to run much closer together.

Alongside ETCS, existing lineside signals are being retained throughout the core for non-ETCS-fitted trains, while also providing a useful backup should it fail.

A traffic management (TM) system will also operate within a wider area of the core ( broadly covering 20 minutes’ travel time in all directions) from later this year to help keep performanc­e as close as possible to the timetabled path of each train, and to mitigate the risk of late-running services.

Linking TM to Automatic Route Setting software will also help signallers based at Three Bridges Rail Operating Centre (TBROC) to recover the timetable in case of disruption.

The task of delivering this infrastruc­ture falls to Network Rail’s Thameslink Programme High Capacity Infrastruc­ture (HCI) team, led by project director Martin Chatfield.

Based near Blackfriar­s station at James Forbes House ( JFH), HCI began its journey in 2012 to extensivel­y test and commission the digital signalling technology, both hardware and software, before it is pressed into full service in May.

The team’s challenge is unique within NR. ETCS has never before been deployed on this scale on a UK main line. Another team is also working to install ETCS on Crossrail’s western section, but ETCS Level 2 has never been overlaid onto existing systems in combinatio­n with ATO, as is the case with Thameslink.

Elevating its status even further, Thameslink is of great interest to NR’s Digital Railway team. Thameslink is an entirely independen­tly governed programme from DR, but it will act as a benchmark for the migration of ETCS to other parts of the network in Control Period 6 (April 2019March 2024) and beyond.

Chatfield explains: “Getting to this point

Thameslink passengers will be getting a metro-style railway like the London Undergroun­d - but with much better views. Martin Chatfield, Project Director, Network Rail

hasn’t just happened overnight and the software wasn’t suddenly just switched on. Until 2019 the industry will be continuing to work incrementa­lly to get up to 24tph. We are also providing the tools to allow TOCs to manage the PPM (Public Performanc­e Measure) for up to 700 daily Thameslink services.

“Since 2012 we’ve been working hard on three work packages: deploying the ATO and ETCS to create reliable 24tph capability, managing the necessary signalling re-controls and traffic management introducti­on, and carrying out a number of station enhancemen­ts to help reduce dwell times.”

Chatfield is keen to stress the importance of the last point, as high frequencie­s cannot be maintained through the core without reducing dwell times at stations from their current two-three minutes, to less than 60 seconds.

To help achieve this, mobility ramps have been installed mid-platform at all core stations to expedite wheelchair access, while passenger informatio­n screens will be improved and station signage increased.

He adds: “It’s not just been about providing a system to run 24tph, but having a whole-system approach in order to change passenger behavior.

“We’re trying to concentrat­e on talking up the benefits of this, as Thameslink passengers will be getting a metro-style railway like the London Undergroun­d - but with much better views.

“That means that trains will be pulling into stations as the tail lights of the one in front are still disappeari­ng from view, which I don’t think all Thameslink passengers will be used to.

“New and improved signage and informatio­n screens will help with that [transition], and help maintain performanc­e throughout the core.”

Testing of ETCS and ATO commenced in 2013, following the opening of a purposebui­lt lab at JFH containing an exact replica of a Class 700 cab.

Dynamic testing then began at Network Rail’s ETCS National Integratio­n Facility (ENIF) at Hitchin approximat­ely a year later using NR’s Class 313 ERTMS test train on a specially designated section of the Hertford Loop line.

The HCI team then switched to overnight testing on the core itself, in April 2016, using a Class 700 train specifical­ly provided for this purpose by Siemens.

Chatfield adds: “We used ENIF for a couple of years and the ‘313’ while we awaited our own Class 700, which we tested there before taking it into the core. I guess that means we must be one of the only NR projects to have ever been given our own train.”

RAIL was invited to tour the lab at JFH on February 19, where it is given a tour and demonstrat­ion of the simulator by senior programme engineer David Harris.

As the only facility of its type in the UK, Harris says that two or three requests are received every month to visit the lab by

a range of suppliers, operators and other industry bodies.

This offline testing centre contains at least one sample of each component needed to run ETCS and ATO. This includes a dummy balise (ETCS transponde­r), a balise reader, AWS and TPWS (which would provide train protection if ETCS fails), GSM-R connection, all on-board equipment, plus real trackside interlocki­ngs and a radio block controller.

The laboratory has the capacity to simulate 60 trains and to operate any one of them in order to replicate the connection that trains will have with other equipped trains in the core.

It will remain in use with HCI until at least November when a further use will be found for it.

“All of this is real kit,” adds Chatfield. “There are balises, interlocki­ngs and a doppler radar downstairs, so we’ve got an entire railway in a double-storey Portakabin.

“We’ll try and find a purchaser for it when we’re finished, perhaps within NR, or offer it as a maintenanc­e facility to the routes or equipment maintainer­s.”

RAIL then heads almost 30 miles south to Three Bridges Rail Operating Centre (TBROC), where control and signalling of the Thameslink network is being consolidat­ed into a single site.

On the first floor, new workstatio­ns have been installed and are fully operationa­l for the Thameslink core’s north and central sections, having already been re-controlled from West Hampstead and Victoria.

Elsewhere in the room, there are workstatio­ns for London Bridge, Charing Cross and Cannon Street A and B. Work has also begun to accommodat­e panels from Lewisham and Grove Park in May. There will also be a screen for the traffic management system that will be run in shadow mode and then become fully operationa­l in early 2019, when it will become interfaced with signallers’ workstatio­ns via Automatic Route Setting.

Meanwhile, on the ground floor, full training for ETCS, ATO and TM is being delivered in a simulator room for the 24 signallers based at TBROC. Not only will

We must be one of the only NR projects to have ever been given our own train. Martin Chatfield, Project Director, Network Rail

they have to be able to work with the new systems, but they must be able to signal trains in the convention­al fashion and switch back to lineside signalling in the event of ETCS failure.

Looking ahead, and Chatfield says that the existing infrastruc­ture could support the introducti­on of 24tph by the end of 2018 as originally envisaged.

In fact, it could potentiall­y support 30tph, although this would be reserved for times of extreme disruption-only as some services would be required to run nonstop, undoubtedl­y inconvenie­ncing some passengers.

The industry has agreed that it would be beneficial to passengers to introduce the timetable in four phases, to enable experience to be embedded between stages.

As for Chatfield and his approximat­ely 35-strong HCI team, they have been incorporat­ed into NR’s Infrastruc­ture Projects signalling team and seconded back to Thameslink, so that its digital signalling capabiliti­es are not lost at the end of the programme next year.

They may then be deployed to the possible future Digital Railway projects which were outlined in NR’s CP6 Strategic Business

Plan, published on February 13, such as resignalli­ng schemes at Feltham or on the southern portion of the East Coast Main Line into King’s Cross and Moorgate.

Chatfield welcomes the opportunit­y to continue the pioneering work of Thameslink, and to cultivate more talented young engineers.

“There’s a very collaborat­ive team here with our technology suppliers Siemens and Hitachi Rail Europe. ETCS engineers weren’t exactly growing on trees in 2012, and they still aren’t, so it has been a very open process with suppliers, which will be carried through to the next schemes.

“The amount of staff developmen­t here during testing has been phenomenal, however, and we’ve had three or four graduate engineers move on to highly skilled jobs abroad and elsewhere in the supply chain, and that cycle continues.

“Upskilling has always been very important to me and keeping hold of people has been quite difficult, but we have been very successful at providing career paths and hopefully we will now provide the industry with lots of future capability.”

 ?? NIGEL HARRIS. NIGEL HARRIS. ?? The view from Govia Thameslink Railway 700128 on February 26. The train is the 0946 Peterborou­ghHorsham, and is about to turn right into the Canal Tunnels, which will take it from the East Coast Main Line and into the ‘Core’ under St Pancras Internatio­nal. This was the first through train from the Great Northern to the Southern region. GTR 700128 about to enter Canal Tunnels.
NIGEL HARRIS. NIGEL HARRIS. The view from Govia Thameslink Railway 700128 on February 26. The train is the 0946 Peterborou­ghHorsham, and is about to turn right into the Canal Tunnels, which will take it from the East Coast Main Line and into the ‘Core’ under St Pancras Internatio­nal. This was the first through train from the Great Northern to the Southern region. GTR 700128 about to enter Canal Tunnels.
 ??  ??
 ?? NETWORK RAIL. ?? Opened in January 2014, Three Bridges ROC controls signalling through Thameslink’s central core, and is one of 12 Network Rail rail operating centres that will eventually control the entire network across the UK.
NETWORK RAIL. Opened in January 2014, Three Bridges ROC controls signalling through Thameslink’s central core, and is one of 12 Network Rail rail operating centres that will eventually control the entire network across the UK.
 ?? PAUL STEPHEN. ?? All 24 signallers at Three Bridges have received three days of training and assessment in ETCS and ATO in the rail operating centre’s ground floor simulator room. A further four to five days training is provided for traffic management. Left and above: HCI’s system integratio­n laboratory at James Forbes House in Southwark enables the offline testing of ETCS and ATO equipment using real equipment and a Class 700 simulator. PAUL STEPHEN.
PAUL STEPHEN. All 24 signallers at Three Bridges have received three days of training and assessment in ETCS and ATO in the rail operating centre’s ground floor simulator room. A further four to five days training is provided for traffic management. Left and above: HCI’s system integratio­n laboratory at James Forbes House in Southwark enables the offline testing of ETCS and ATO equipment using real equipment and a Class 700 simulator. PAUL STEPHEN.
 ?? NETWORK RAIL. ?? ETCS technology incorporat­ed by Thameslink was tested at the ETCS National Integratio­n Facility at Hitchin and on the Hertford Loop line near Watton at Stone, where ETCS marker blocks can clearly be seen.
NETWORK RAIL. ETCS technology incorporat­ed by Thameslink was tested at the ETCS National Integratio­n Facility at Hitchin and on the Hertford Loop line near Watton at Stone, where ETCS marker blocks can clearly be seen.
 ?? PAUL STEPHEN. ?? Left and adove: The Thameslink core central workstatio­n at TBROC is pictured left, alongside a wider view of the operations room on February 19.
PAUL STEPHEN. Left and adove: The Thameslink core central workstatio­n at TBROC is pictured left, alongside a wider view of the operations room on February 19.
 ?? ANTONY GUPPY. ?? GTR 700041 passes an ETCS track block marker as it departs City Thameslink with a Three Bridges-Bedford service on February 15. These services will remain convention­ally signalled until May when the ‘700s’ will switch to in-cab signaling and ATO.
ANTONY GUPPY. GTR 700041 passes an ETCS track block marker as it departs City Thameslink with a Three Bridges-Bedford service on February 15. These services will remain convention­ally signalled until May when the ‘700s’ will switch to in-cab signaling and ATO.

Newspapers in English

Newspapers from United Kingdom