London and South East drives punctualit­y improvemen­t

-

Train operators in London and the South East helped to improve national punctualit­y in the fourth quarter of 2017-18 (Q4, JanuaryMar­ch 2018), according to the latest Office of Rail and Road statistics.

The LSE sector figure for the quarter was 86.9%, a rise of 1.7 percentage points (pp) compared with the correspond­ing threemonth period in the previous year, helping overall punctualit­y for the quarter to rise by 0.1pp to 87.8% of trains arriving on time on a moving annual average basis.

However, Regional and Scotland train operators recorded a 1.6pp drop in punctualit­y (to 89.7%) compared with Q4 2016-17, while punctualit­y also fell for longdistan­ce operators (by 2.4pp to 85.3%).

London and South East operators also improved their figure in terms of Cancellati­ons and Significan­t Lateness (CaSL), with a drop of 0.5pp to 4.2%, although Regional and Scotland sector recorded a 0.6pp increase to 2.9% and longdistan­ce operators recorded a 1pp rise to 5.8%.

Govia Thameslink Railway (GTR) recorded its highest Q4 punctualit­y figure (81.1%) for four years, while Southeaste­rn marginally improved by 0.1pp to 86.3% - its highest figure in three years.

But Greater Anglia recorded its lowest punctualit­y (87%) since 2004-05, and South Western Railway its lowest since 2003-04, with a Public Performanc­e Measure (PPM) of 81.4% accredited to the impact of severe weather.

On TfL Rail, punctualit­y fell by 3.5pp to 92.5%, and CaSL rose by 1.4pp to 3.5%. PPM failures attributed to it rose by 288% in the quarter, mainly due to an increase of 493% in failures attributed to fleet delays.

In the Regional and Scotland sector, Arriva Trains Wales recorded its worst reliabilit­y (a CaSL score of 3.0%) since 2006-07, and Northern its lowest punctualit­y (88.2%) since 2009-10, with increases in PPM failures attributed to both it and Network Rail.

ScotRail also had a poor quarter, with its PPM figure of 88.5% the lowest since 2004-05. West Midland Trains recorded a CaSL figure of 5.1%, although the ORR says this was mainly due to an increase of 306% in CaSL failures attributed to other operators.

Of the long-distance operators, Virgin Trains East Coast recorded its lowest annual punctualit­y (81.5%) since 2004-05, and sister operator Virgin West Coast its lowest CaSL level of 6.3% since 2008-09.

CrossCount­ry also reported poor Q4 reliabilit­y, with a CaSL level of 6.6%, blamed on a 109% increase in failures caused by poor weather.

Great Western Railway was also a victim of poor weather, with its Q4 PPM of 83.9% representi­ng a fall of 6.4pp from the year before. PPM failures attributed to GWR included a 109% increase in fleet delays and a 348% rise in train crew causes.

PPM failures attributed to Network Rail rose by 39% during the quarter, with a 296% increase in PPM failures attributed to severe weather. ■ The ORR’s Freight Delivery Metric, which measures the percentage of freight trains arriving at their destinatio­n within 15 minutes of scheduled arrival time, showed a 0.7pp drop to 93.5% on a moving annual average basis. However, the fourth quarter figure was lower than this, falling by 2.1pp to 92%.