Rail (UK)

A 22nd century solution to a 21st century problem

Siemens and Network Rail collected this year’s Infrastruc­ture Project of the Year accolade at RAIL’s National Rail Awards for their successful Birmingham New Street Phase 4 & 5 renewals. PAUL STEPHEN reports

-

Birmingham New Street is the sixth busiest station in the UK and the busiest outside London, with some 42.3 million entries and exits registered between April 2016 and March 2017. It is also the busiest interchang­e station outside London. Nearly 170,000 passengers change trains at New Street on a daily basis, owing to its status as a major hub on both the cross-country network and the West Coast Main Line.

But with increasing demand for public transport, it is forecast that rail travel between London and Birmingham will double in the next 20 years. Action was required, to prepare the station to accommodat­e that future growth and to keep pace with demand.

A complex multi-disciplina­ry feat of economic and strategic engineerin­g, the Birmingham New Street Phase 4 & 5 renewals represente­d the start of a portfolio of renewals across the local network.

The £47 million project has also been described by Network Rail as “a 22nd century solution to a 21st century problem”, due to its use of renewable, interchang­eable and expandable infrastruc­ture that will make allowance for the future requiremen­ts of HS2 and NR’s Digital Railway programme.

And it was a worthy winner of National Rail Awards Infrastruc­ture Project of the Year, with the prize going to Network Rail and Siemens.

Commencing in 2015, the two-year scheme focused on the renewal and remodellin­g of track and signalling equipment at four major junctions controlled by Birmingham New Street Power Signal Box (PSB), which itself handled 80% of daily total services to the city. Control of the operationa­l railway is also gradually being transferre­d from the PSB to the West Midlands Signalling Centre at Saltley, as further phases are completed.

Much of the existing equipment was around 50 years old, and managing levels of traffic that were unimaginab­le when the system was commission­ed in the 1960s.

Five years of developmen­t enabled many alternativ­e approaches to be considered for the renewals work, and it was recognised by NR and Siemens early on that an innovative, collaborat­ive partnershi­p was the only way that the project could be delivered to such a demanding schedule.

A Collaborat­ive Management Team was set up comprising representa­tives of NR, Siemens, S&C Alliance and other sub-contractor­s. A series of inter-organisati­onal working groups was also establishe­d to collaborat­e on areas of the programme including safety, route access, design, social and environmen­tal sustainabi­lity, commercial behaviours and constructi­ons.

A Project Charter meant promotion of a culture of openness, transparen­cy and honesty - to ensure that a true ‘one-team approach’ was adopted by the programme’s 200+ full time staff, and to drive collaborat­ion, innovation and outstandin­g performanc­e.

The combined team felt this project spirit would decree that all participan­ts would win or all would lose based on the project’s outcomes, and that mistakes were seen as an opportunit­y to improve rather than attach blame or finger point.

The scheme itself was executed in three stages, moving south to north so that surroundin­g stations could remain open throughout constructi­on and to minimise disruption.

In just two years, the project achieved the resignalli­ng of five ELRs (engineers’ line references) and the incorporat­ion of new telecoms nodes that had never been installed before. Meanwhile, 80 trains per hour continued to operate from 12 of Birmingham New Street’s 13 platforms.

Over those two years, every project milestone was met, ensuring that the full functional­ity of the revised and resignalle­d network could be delivered on time.

The combined team achieved half a million

 ?? PHIL METCALFE. ?? Birmingham New Street Phase 4 & 5 renewals instigated ‘a new way of working’ which Network Rail has adopted as the standard by which all future projects should be measured.
PHIL METCALFE. Birmingham New Street Phase 4 & 5 renewals instigated ‘a new way of working’ which Network Rail has adopted as the standard by which all future projects should be measured.

Newspapers in English

Newspapers from United Kingdom