Rail (UK)

Crossrail suffers indefinite delay

-

Concerns about whether the central section of Crossrail would open in time were raised by then chairman Sir Terry Morgan in a meeting with the Mayor of London and Transport for London (TfL) on July 26 - a month before the decision was formally taken to delay the opening until next year.

The release on December 10 of Crossrail board minutes and meetings with the Mayor and TfL reveal that in a presentati­on given by Crossrail, the December 2018 opening date was said to be at “high risk”.

This was due to a late start of dynamic testing following a voltage transforme­r failure in November 2017; “challenges” to completing the fit-out, testing and commission­ing of the infrastruc­ture; rolling stock that was “less tested and stable than planned for”; insufficie­nt testing time remaining; and poorer than planned productivi­ty.

The presentati­on created three scenarios for when Crossrail might open, with the latest expected to be August 2019. The Mayor of London’s office said in a lengthy breakdown of meetings issued on the same day that “the Mayor is verbally briefed by Crossrail that it [opening] would be well before that [August 2019]”.

At the Crossrail board meeting of July 19, Chief Executive Simon Wright had acknowledg­ed “significan­t pressure” on the amount of work left to complete in the time available. Problems were highlighte­d with signalling software, while less than half of the project milestones required to be delivered by the time of the board meeting had been done.

In a briefing note from Crossrail on August 7, it was confirmed that a revised delivery schedule for the project would be discussed with the Crossrail Ltd board on August 29, followed by the Sponsor Board on September 3 and the Mayor of London on September 6. The briefing note also highlighte­d the fact that radio connection­s supporting the tunnel signalling system were not complete, preventing full testing of rolling stock and signalling together.

In the weekly report of August 13, the Mayor of London’s office claims that the formal forecast date for the start of passenger service remained December 9. It was not until the August 29 Crossrail board meeting that the board confirmed it would not achieve the planned opening date. Since then, the revised ‘autumn 2019’ opening date has been deferred to an unspecifie­d time.

At the release of the papers, London Assembly Transport Committee Chairman Caroline Pidgeon said: “It is now clear that the Mayor was told on July 26 that Crossrail’s opening date was at “high risk”. TfL has released a lot of news today [December 10], but not the informatio­n we asked for. We summonsed TfL’s weekly updates to the Mayor and these have been published, apart from a suspicious missing period in July-August.

“It’s very convenient these documents have been released on the same day it’s announced that Crossrail will receive an eyewaterin­g budget boost from the GLA, as well as a new chairman.”

London Mayor Sadiq Khan said the release of the documents confirms that he has been “fully transparen­t” about what he knew and when, adding: “I remain deeply angry and frustrated at the delays and cost overrun, and these documents are a serious indictment of Crossrail Ltd’s governance. It is clear that as joint sponsors, TfL and the Department for Transport should have been told much more, far sooner, by Crossrail.”

 ??  ??

Newspapers in English

Newspapers from United Kingdom