Rail (UK)

ScotRail in trouble?

- Richard Clinnick Assistant Editor richard.clinnick@bauermedia.co.uk @Clinnick1

ScotRail given eight weeks to improve performanc­e after Scottish Government issues a remedial plan notice.

SCOTRAIL has been told by Transport Scotland that services must improve, and that it has eight weeks to submit plans on how to achieve this.

The Scottish Government issued a remedial plan notice on December 24, after cancellati­ons in the Suburban East Sector exceeded the Breach Performanc­e Level between November 11 and December 8 (Period 9). The area covered is Edinburgh-Bathgate, Dunblane, Fife Circle, Tweedbank and North Berwick.

ScotRail blamed the late delivery of new trains and Inter7City High Speed Trains, plus the need to train staff on them, as a reason for poor performanc­e, as well as an RMT overtime ban that prevented staff training. The operator informed Transport Scotland of the cancellati­ons that indicated a performanc­e breach on December 20.

The remedial plan notice also applies pre-emptively to SR’s overall performanc­e, which is expected to drop below the agreed Public Performanc­e Measure (PPM) during Period 10 (December 9-January 5).

“We have stressed many times that ScotRail must improve, but too often passengers have been left disappoint­ed,” said Michael Matheson, Cabinet Secretary for Transport, Infrastruc­ture and Connectivi­ty.

He added: “This month should have been a celebratio­n of the biggest increase in services and capacity, enabled by our ambitious electrific­ation programme. Instead, we are taking this contractua­l step of issuing a remedial plan notice.”

ScotRail Alliance Managing Director Alex Hynes said: “The disruption has been caused by late delivery of new trains by Hitachi and Wabtec which means the training that is required for our traincrew, on new trains and new routes, has had to be compressed into a very short space of time. Day-to-day services have had to be cancelled to allow our people to take part in training.”

He added: “RMT industrial action meant there was an overtime ban for some of our people, which lasted for several weeks. This is now resolved, but made the problem of traincrew training worse.”

Hynes said training was ongoing and that this will allow services to return to normal, although disruption will continue while conductors and drivers are trained.

Seventy Class 385s are on order from Hitachi, of which 35 are in Scotland. Deliveries should have started in September 2017 ahead of an introducti­on into traffic that December, but that was delayed owing to problems with the trains. This was further compounded by problems with drivers’ visibility.

Class 385s eventually entered traffic in July, and only took over all Edinburgh-Glasgow via Falkirk High services in December 2018 - a year later than planned.

The Inter7City HSTs should have been introduced from last May, but problems discovered in the overhaul and refurbishm­ent meant that was missed. So far, only one of 26 sets is in traffic, with ten ‘classic’ (unrefurbis­hed) sets in use. SR still aims to have all IC7 sets in traffic by the end of 2019.

 ?? PHILIP HAIGH. ?? A Class 385 waits to leave Stirling on December 10 2018, as a ‘classic’ High Speed Train arrives. ScotRail has been told to improve its performanc­e by the Scottish Government, following an increase in the number of cancelled services.
PHILIP HAIGH. A Class 385 waits to leave Stirling on December 10 2018, as a ‘classic’ High Speed Train arrives. ScotRail has been told to improve its performanc­e by the Scottish Government, following an increase in the number of cancelled services.
 ??  ??

Newspapers in English

Newspapers from United Kingdom