Barking Riverside extension: timeline
2008: Proposed Docklands Light Railway extension cancelled.
2014: Gospel Oak-Barking line proposed to be extended.
Mar 2016: Transport and Works Act Order (TWO) submitted.
Oct 2016: Public Inquiry into TWO.
Aug 2017: Secretary of State grants TWO.
Dec 2018: Morgan Sindall Infrastructure and VolkerFitzpatrick appointed as contractors.
Feb 2019: Start of major construction works.
Oct 2021: Completion of viaduct construction including track slab.
Mar 2022: Final signal commissioning completed.
May 2022: Driver training and route testing begins.