Barking Riverside extension: timeline

-

2008: Proposed Docklands Light Railway extension cancelled.

2014: Gospel Oak-Barking line proposed to be extended.

Mar 2016: Transport and Works Act Order (TWO) submitted.

Oct 2016: Public Inquiry into TWO.

Aug 2017: Secretary of State grants TWO.

Dec 2018: Morgan Sindall Infrastruc­ture and VolkerFitz­patrick appointed as contractor­s.

Feb 2019: Start of major constructi­on works.

Oct 2021: Completion of viaduct constructi­on including track slab.

Mar 2022: Final signal commission­ing completed.

May 2022: Driver training and route testing begins.