Scottish Daily Mail

Now SNP admits new Forth bridge is 6 MONTHS late

- By Alan Roden Scottish Political Editor

THE SNP was last night accused of keeping voters in the dark over a delay to the opening of the new Forth crossing.

Economy Secretary Keith Brown was forced to admit the biggest infrastruc­ture project in Scottish history is almost six months behind schedule.

‘Adverse weather conditions’ in April and May have been blamed – yet that only cost the contractor 25 ‘lost days’.

Transport Scotland said the project was on track as recently as March, causing confusion at Holyrood as to how 25 lost days can cause a five-and-a-half month delay.

Tory MSP Murdo Fraser demanded to know if contractor­s were ‘asked to sign confidenti­ality agreements not to disclose this informatio­n until after the Scottish parliament election on May 5’– a suggestion Mr Brown denied.

The delay is an embarrassm­ent for the SNP. Its election manifesto, unveiled in April, said: ‘The £1.4billion Queensferr­y Crossing is on time and on budget.’ Nicola Sturgeon and other ministers have repeatedly boasted about their successful ‘stewardshi­p’ of the project.

Lib Dem MSP Alex Cole-Hamilton said: ‘Much about this statement suggests a project in abject distress. How on earth does 25 days lost to weather in April and May equate to a 180-day delay in opening the bridge? Does he take us for fools?

‘Does he now expect parliament to believe the first ministers learned of this was just, convenient­ly, days after the Scottish election?’

Engineers had hoped to complete the bridge by December 2016 but that timescale has now slipped.

In a statement to parliament, Mr Brown said contractor Forth Crossing Bridge Constructo­rs (FCBC) submitted an update of the impact of the weather last week, adding: ‘Since deck-lifting operations com-

‘A project in abject distress’

menced in September 2015, the downtime due to adverse weather, specifical­ly wind, has been 40 per cent compared to the 25 per cent anticipate­d by the contractor.

‘Until May, FCBC believed they could mitigate these weather effects. However, the impact of the weather in April and May was particular­ly severe, with 13 days and 12 days lost respective­ly.

‘As a result, FCBC have advised ministers that due to the combined effects of the time lost in these two months they can no longer deliver the December 2016 target opening date. It is important to remind parliament the contractua­l completion date for the bridge is actually June 2017. December 2016 was a target date that would have seen the bridge open six months ahead of contract.

‘The Queensferr­y Crossing is now expected to be open by mid-May 2017, prior to the contractua­l completion date of mid-June 2017. There will be no additional cost to taxpayers. Our previous projection of a £245million saving remains.’

Mr Fraser asked: ‘Is it true that contractor­s working on this new bridge were aware of the delay some weeks ago and were asked to sign confidenti­ality agreements not to disclose this informatio­n until after the Scottish parliament election on May 5?’

Mr Brown replied: ‘I have no knowledge of, and certainly the Scottish Government has never entered into, any confidenti­ally agreements with the contractor saying that they cannot speak about this.’

Comment – Page 16

 ??  ?? Lost days: The new Queensferr­y Crossing in April
Lost days: The new Queensferr­y Crossing in April
 ??  ?? Boastful: Nicola Sturgeon at the bridge
Boastful: Nicola Sturgeon at the bridge

Newspapers in English

Newspapers from United Kingdom