BBC accused of ‘outrageous overspend’ by splurging £87m of YOUR cash on new set to make soap HD-ready ++ Project is staggering £27m over budget ++ And it’ll be nearly 5 years late

- By Susie Coen TV and Radio Reporter s.coen@dailymail.co.uk

THE BBC has been accused of ‘outrageous­ly overspendi­ng’ licence fee cash after it emerged that EastEnders’ new set will cost £86.7million.

That is £27million over the original budget – and the project is expected to be nearly five years late.

Work to rebuild and extend Albert Square was due to be completed in August at a cost of £59.7million. But a damning National Audit Office report published today finds that the BBC’s poor planning and lack of expertise means it will cost 45 per cent more, and will not be completed until May 2023.

The NAO says the Corporatio­n ‘will not be able to deliver value for money’ with the project, named E20 after the soap opera’s fictional Walford postcode, which is being funded entirely from the £150.50a-year TV licence fee. The current East- Enders set at Elstree Studios in Hertfordsh­ire was built in 1984 using steel frames, plywood and plaster brick panels. It was intended to last only two years.

The poor quality of constructi­on means high-definition filming is not possible, while health and safety concerns have caused delays to filming.

The BBC is building a new ‘front lot’ – a brickwork replica of the current set – and a ‘back lot’ which will provide extra locations to ‘better reflect modern East End London’. It has been reported that one of the new locations will be a mosque.

The front lot is now expected to cost £54.7million – 75 per cent more than planned – after it took 11 months for the BBC to negotiate with its contractor Wates.

Constructi­on there has only just begun, while the back lot is still ‘at an early design stage’.

Responsibi­lity for the E20 project lies with Richard Dawkins, the £195,000-a-year chief operating officer of BBC Content.

The NAO report finds that early planning processes led to ‘underestim­ation of aspects of complexity, cost and risks’.

It says aspects of the design process were not assessed adequately, the BBC was over- optimistic and its staff ‘had insufficie­nt expertise in constructi­on project management to identify critical issues’.

The Corporatio­n tried to blame £9.2million of the cost increase on inflation and demand for constructi­on services, but was ‘unable to provide evidence’ to support the figure, the NAO says.

Critical design stages were completed without appropriat­e approval and there was ineffectiv­e communicat­ion between the programme and production teams.

This led to the production team making more than 70 requests for design changes – eight months after the design was supposed to have been agreed. These resulted in 16 changes and cost around £440,000, the NAO says. The project did encounter problems with asbestos and obstructio­ns that were ‘to some extent unforeseen’, but this was ‘partly due to poor BBC site records, and limited surveying work’, it adds.

Sir Amyas Morse, the head of the NAO, said: ‘The BBC will not be able to deliver value for money on E20 in the way that it originally envisaged. It is surprising that some of the reasons for this were built in from the beginning. Despite recent project management improvemen­ts, E20 is late and over budget against its 2015 plans.

‘Given the high-risk nature of E20, it will need close scrutiny until it is finished.’

EastEnders once regularly attracted 20million viewers per episode but now struggles to attract 7million.

Liberal Democrat MP Layla Moran said: ‘The Queen Vic and Albert Square are dear to my heart, like lots of people, and there is no doubt in recent years the show has played a major role is raising many important societal issues. However I can’t imagine any of the straight-talking characters accepting this outrageous overspend of public money.’

Labour MP Meg Hillier, chairman of the public accounts committee, said: ‘It is concerning that the BBC has been unable to keep to budget and time. It is critical, given the BBC’s funding pressures, that every pound of licence fee payers’ money is spent effectivel­y.’ Labour MP Chris Evans, who sits on the committee, added: ‘They’re investing in a programme that is not as popular as it once was, and they really need to start thinking about investing in the long term and in projects that can be useful for other things other than just one programme.

‘The BBC ought to realise that the licence fee is still unpopular. Many people are asking about value for money. At the end of the day, this isn’t their money, this is licence fee payers’ money.’

The BBC said: ‘The set of EastEnders was built in 1984 and only intended for use for two years. Over 30 years later, the show remains one of the BBC’s flagship programmes and yet is filming from a set that is no longer fit for purpose.

‘The new set is a large, complex project which has already delivered many other vital improvemen­ts at Elstree, but like any building work of this scale there have been challenges, including constructi­on market issues beyond our control. We’ve already made improvemen­ts and are keeping the project under close scrutiny.’

‘Not able to deliver value for money’

 ??  ?? Worn-out Walford: The current EastEnders set was built in 1984 and designed to last two years
Worn-out Walford: The current EastEnders set was built in 1984 and designed to last two years