KEY CONCERNS OVER YARD...

-

■ There is a disconnect between the level of productivi­ty required to meet targets and the productivi­ty the yard delivers.

■ There is significan­t programme slippage and high-level progress milestones have been missed.

■ Many work packages pursued in January were either over-resourced or suffered from a lack of equipment or consumable­s.

■ Efficiency remains low due to what CMAL considers to be an ineffectiv­e communicat­ion strategy.

■ Despite efforts to work smarter, programme start and completion dates continue to be missed.

■ CMAL considers management of project dependenci­es, weaknesses in the planning of the build and poor supervisio­n to be key issues.

■ Risk and change management planning remains inconsiste­nt with normal commercial shipbuildi­ng practice.