Steam Railway (UK)

BRITAIN’S BIGGEST NEW-BUILD BOILER COMPLETED FOR WHR GARRATT

-

Northern Steam Engineerin­g Ltd has completed what it claims to be the biggest boiler to be finished in Britain since the BR era.

The boiler, ordered for Welsh Highland Railway-based ‘NGG16’ 2-6-2+2-6-2 No. 130, was lifted onto the Garratt’s frames at Dinas on December 12. It is believed to be the largest engine boiler completed in Britain since 1966, when Hunslet built four spare 4-8-2 boilers for export to Sudan (SR450).

At 18ft long (including the smokebox), with a diameter of 4ft 9½in and a grate area of 19½sq. ft, the boiler is comparable in size to a Standard ‘2MT’ tank’s pressure vessel, albeit shorter and with a larger grate area.

Designed and built entirely in-house by NSE staff under the supervisio­n of Project Director and Lead Boilersmit­h Adam Dalgleish, the boiler is of partrivete­d, part-welded design which takes into account the external dimensions of the original design and the requiremen­ts of modern safety standards.

 ?? CHRIS PARRY/FFWHR ?? ‘NGG16’ No. 130’s new boiler is lowered onto the Garratt’s frames at Dinas on the Welsh Highland Railway on December 12.
CHRIS PARRY/FFWHR ‘NGG16’ No. 130’s new boiler is lowered onto the Garratt’s frames at Dinas on the Welsh Highland Railway on December 12.

Newspapers in English

Newspapers from United Kingdom