Stirling Observer

How saga unfolded

-

March 2021

Stirling Council closed the Branshogle Bridge, on the B818, after a partial collapse. Council contractor­s then feared that a further collapse was likely and a full road closure was put in place. May 2021

Farmers and HGV drivers Were facing a 19-mile diversion as a result of the road closure. The closure meant that lorries looking to head along the route between Balfron and Fintry had to take a lengthy detour via Buchlyvie, Arnprior and Kippen. Vehicles trying to access Claylands Farm, along the B818, faced an almost 19-mile diversion to access the property. The farm sits less than a mile from the closure site, but delivery lorries had to divert through Balfron and along the A811, travelling through Buchlyvie, Arnprior and Kippen, then on to the B822 to Fintry before travelling east along the B818 to the farm.

The farmer there said delays were having a“major impact on three businesses that supply food, fuel and power”to local people.

June 2021

A survey was carried out to determine the scale of repairs required on the bridge.

Stirling Council said that the consultant­s were undertakin­g the study to decide on the appropriat­e course of action to reopen the route. September 2021

Disappoint­ment was expressed over the length of time being taken to repair the bridge.

Nearby residents and businesses raised concerns over the length of diversion as well as the volume of traffic forced onto other surroundin­g roads.

In August, council officers staged online meetings with those affected by the closure to address concerns.

Among the questions raised with council officers was that of putting a temporary structure in place in order to re-open the route, which was kicked into touch.

November 2021

It was claimed that traders in west Stirlingsh­ire could see takings drop by up to 40 per cent due to prolonged bridge closures in the area.

Business owners in Drymen, Croftamie, Balmaha and the

East Loch Lomond area said that multiple bridge closures in the area, including the Branshogle Bridge, had brought businesses to their knees and they formed a community action group comprising of 80 per cent of the businesses.

December 2021

Stirling Council confirmed to the Observer that a contractor has been appointed to carry out repairs on the bridge and commenced works on site on November 29. The structural improvemen­ts were anticipate­d to take 18 weeks – meaning that work should have been finished in early April.

April 2022

The completion of works to repair the structure was delayed by more than two months.

Stirling Council confirmed to the Observer that the work had hit a series of delays and was due for completion in late June. A Stirling Council spokespers­on said:“we wrote to the affected communitie­s and residents last week to confirm that work on the Branshogle Bridge has unfortunat­ely encountere­d unforeseen delays.

“This is an environmen­tally sensitive site that represents significan­t access and constructi­on challenges. Works have exposed more complex ground conditions than originally identified that require significan­t changes to the design, constructi­on process and temporary support works.

“Progress has also been affected by recent storms and high water levels, with work now expected to be completed by the end of June.

“We are aware of the impact the closure is having on the community and the council is working closely with the contractor to ensure repairs are completed as soon as possible.”

Newspapers in English

Newspapers from United Kingdom