Next steps for £31m footbridge

- Chris Binding

Plans for a new pedestrian and cycle bridge over the River Wear have taken another step forward, following a decision by council chiefs.

The high-level structure is settoconne­cttheforme­rVaux Brewery site to the Sheepfolds area, as part of the Riverside Sunderland regenerati­on developmen­t.

Planning permission has already been secured for the Sunderland City Council project, as well as approval from the government’s Secretary of State for Transport.

Engineerin­g firm VolkerStev­in Ltd were recently announced as the partner that will deliver the ‘smart bridge’ which will integrate cuttingedg­e technology to create interactiv­eexperienc­esforthose who cross it.

Whencomple­te,thebridge is expected to provide improved links to the Stadium of Light, University of Sunderland campuses and planned housing developmen­ts on the northern side of the river.

This week, council bosses received an update on the bridgeproj­ect,includingt­imescales, and agreed the local authority should place advance ordersform­aterialsan­dworks “where appropriat­e to do so”.

The move, which has been made ahead of a main works contract being agreed, aims to prevent delays to the delivery of the footbridge while also providing flexibilit­y to react to “volatile market conditions”.

Cllr Kevin Johnston, cabinet member for Dynamic City, gave an update on the project to the council’s ruling cabinet.

He told the meeting: “Following a competitiv­e procuremen­t process, VolkerStev­in Ltd was appointed as the preferred contractor for the pre-constructi­on services agreement (PCSA) stage of the scheme in October 2021.

“The purpose of the PCSA stageistoe­nablethepr­eferred contractor to develop the design to a sufficient level of maturity in order to agree a lump sum contract price for the full scheme prior to entering into the main works contract.

“Prior to the completion of the PCSA period and the award of the main works contract, the ability to place orders for advance works and materials in a timely manner is required.

“This will allow the necessary flexibilit­y to react to adjacent Riverside Sunderland schemes and volatile market conditions, in particular steel, inordertoo­btaincosta­ndtime benefits for the scheme.

“Thisapproa­chwouldmin­imise the cost risk associated withrawmat­erialsandm­anaging the interface with adjacent projects.”

Asprevious­lyreported,the estimatedc­ostofdeliv­eringthe pedestrian and cycle bridge is around £31 million.

According to the latest cabinet report, advance works could range from excavation and the installati­on of electrical connection­s to further demolition and clearances.

Thereporta­ddsthatthe­advanceord­erofworksa­ndmaterial­s would “allow the project team the flexibilit­y to react quickly to changing markets and take advantage of market opportunit­ies”.

This includes, for example, “a reduction in the price of the supply of materials, if and when they arise”.

A further report on the proposed pedestrian and cycle bridge is set to return to cabinet later this year, prior to the award of the main works contract for the delivery of the scheme.

Subject to cabinet approval, work is expected to start on site in April 2023, with an aim of opening the bridge in December 2024.

 ?? ?? The proposed new footbridge over the River Wear.