Teesside Evening Gazette

PD Ports ‘clear winner’ in fight over land access

SOUTH TEES DEVELOPMEN­T CORPORATIO­N AND TEESWORKS LTD ORDERED TO PAY AN ESTIMATED £1.2M IN COSTS, WITH MORE YET TO BE DECIDED

- By NAOMI CORRIGAN Local democracy reporter naomi.corrigan@reachplc.com

A JUDGE has ruled that the South Tees Developmen­t Corporatio­n and Teesworks Ltd must pay the vast majority of the costs incurred by PD Ports after a High Court battle over access routes.

Mr Justice Rajah said, in principle, PD Ports should receive 80% of costs incurred prior to September 21 last year, when an offer to settle by the port operator was rejected, and 100% of its costs thereafter. PD Ports said figures are still be finalised. However, their estimated costs at the end of the trial stood at £2.73m.

The port operator also said STDC and Teesworks Ltd have been instructed to pay an interim cost within the next 14 days, estimated to be in excess of £1.2m, with further costs to be awarded following “a detailed assessment”.

An additional hearing will take place to determine the exact amounts, they said.

Meanwhile, Teesworks has released a statement, revealing it intends to appeal the judgement made in the case while a spokespers­on for STDC said they will not.

The legal case was brought by the publicly-owned STDC – run by the Tees Valley Combined Authority with mayor Ben Houchen at its head – as to whether port operator PD Ports had access to its own land holdings across the Teesworks redevelopm­ent site.

Following a six-week trial, the judge Mr Justice Rajah found PD Ports had establishe­d six of its access claims over three key routes on the site, which was acquired by STDC and its land-owning company South Tees Developmen­ts Limited (STDL), while four claims ruled in STDC’s favour.

At a subsequent High Court hearing on Wednesday to address costs, Mr Justice Rajah said PD Ports was “clearly the successful party”.

“In these proceeding­s, the claimant [STDC] and third party [Teesworks] have maintained that the defendant has no rights of way across its land and has sought declaratio­ns to that effect,” he said.

“The defendant has establishe­d that it has rights of way over three significan­t routes, including importantl­y, the emergency secondary access to Teesport over South Bank.

“On the face of the issues at trial, the defendant has clearly won by establishi­ng a right to emergency access and egress; the rights to which the claimants and third parties thought carried a ransom value.

“It has also establishe­d other rights of access to South Gare and rights of access to Redcar Quay which the claimant and third party have sought a declaratio­n that the defendant did not have.”

Regarding conduct, he said the only matter he was going to take into account related to an offer made by PD Ports to the claimants, two weeks before the trial, which he said was rejected “out of hand”.

In real terms, PD Ports had substantia­lly beaten that offer, he said, establishi­ng rights of way over South Bank, including emergency rights of access.

He said they had matched what it had offered in respect of an access route to South Gare and “almost matched” what it offered to accept in respect of Redcar jetty. “Had that offer been accepted, significan­t parts of the costs of the trial would have been avoided,” he said.

“I say significan­t parts because, of course, there were costs incurred prior to that offer being made but the defendant [PD Ports] says those costs, just to give an idea of all parties, may be between £1.5m and £2m which have been incurred since that offer was rejected.

“The reality is no attempt was made to engage with this offer... I would be very surprised if it had not been possible to reach an agreement which would have avoided this trial.”

The judgement in the case outlined that in PD Ports’ revised schedule, which was served in July last year before the trial began, there were 15 separate categories of rights claimed.

However in its trial skeleton argument, PD Ports abandoned many of its claims to rights of way.

Mr Justice Rajah said the idea that the abandoned claims meant that the claimant and third party had won before the trial had started was, in his judgement, “simply wrong, having regard to what those abandoned claims actually added to the substantiv­e issues between the parties.”

He said the abandoned claims did not affect his assessment that PD Ports was “clearly the overall winner”. The general rule, he said, is that the PD Ports would therefore entitled to be paid costs by STDC and Teesworks.

“The significan­t issue in this case is that, is at the outset of the trial, the defendant abandoned a raft of claims to other arguments and claims to rights of way of many other routes,” he said. PD Ports had not “pinned down its claims it was advancing” until the start of trial and that it was “simply too late” and “should have been dealt with a long time ago”, he said.

STDC and Teesworks had incurred costs for preparing to deal with these issues at trial. However the judge accepted they were “largely secondary claims or alternativ­e claims”. Regarding those abandoned claims, Mr Justice Rajah said, in principle, a deduction of 20% should be made to reflect those costs. Addressing a suggestion the claims had been made to impede building on the land, he said there was no evidence that building had been held back.

A spokespers­on for Teesworks Limited said: “Teesworks Limited welcomed the judgment’s confirmati­on that no rights existed preventing the developmen­t of the Teesworks site. However, after further careful examinatio­n of the Court Judgment and legal advice, Teesworks Limited now intend to submit an applicatio­n to the Court of Appeal, challengin­g several other matters contained within the Judgment which, in the opinion of Teesworks Limited, were wrongly applied. The Court of Appeal applicatio­n will be submitted without delay.”

A spokespers­on for the STDC said its focus has always been “to clarify PDT’s rights to accommodat­e them and prevent hindrance to future economic developmen­t”, adding: “STDC made extensive effort to avoid legal action but the lack of documentar­y evidence supporting PDT’s claim left no option other than to seek a legal determinat­ion. The judgment has now clarified the rights of respective parties.”

In a statement, PD Ports said: “We are grateful for the court’s acknowledg­ement that PD Ports was the successful party... and that a substantia­l interim payment be made in our favour, pending a detailed assessment of the full cost award owed to PD Ports. We estimate the interim payment alone may be in excess of £1.2m.”

Michael McConnell, group property director, said: “The court has affirmed that we were forced into unnecessar­y court action which was not of our choosing. The judgment underlines that the decision by South Tees Developmen­t Corporatio­n and Teesworks to press ahead with legal action – despite the weight of evidence in PD Ports’ favour and our repeated offers of a flexible solution to entirely accommodat­e their developmen­t needs – was entirely unnecessar­y.

“PD Ports made numerous attempts to work with STDC and Teesworks prior to the court action and repeatedly offered, at nil cost, the ability to have our historic prescripti­ve rights of access across STDC land realigned in order to enable any proposed commercial developmen­t. That STDC, a public body with responsibi­lity for the economic regenerati­on of Teesside, would choose to persist with legal action, backed by Teesworks Limited, against PD Ports – the largest private employer and biggest driver of inward investment in the region which should be viewed as a strategic partner – is disappoint­ing and frustratin­g.”

 ?? ?? Land at South Gare, Redcar, was at the centre of the access dispute
Land at South Gare, Redcar, was at the centre of the access dispute

Newspapers in English

Newspapers from United Kingdom