The Arran Banner

Delay hits new ferry terminal

-

Brodick’s new £30 million ferry terminal will not open in August as planned, it emerged this week.

Instead it is likely to be October at the earliest before passengers will get to use the new pier facilities. This is due to a delay in the passenger access system (PAS) currently being built in Spain. The delay is all the more frustratin­g as the main site contractor­s, George Leslie Ltd, will complete the redevelopm­ent of the ferry terminal and pier in August, on time and on budget.

However, Adelte, the specialist contractor appointed through a separate tender process to design and install the PAS at a cost of £1.5 million, which is currently under constructi­on outside Barcelona, has experience­d delays, impacting on the completion date of the overall project. The completion of the works at the new terminal is now scheduled to be late September or early October. On completion, CMAL will handover the terminal

to CalMac, which will need a few weeks to make it operationa­l.

The delays have been caused by technical issues relating to the fabricatio­n stage, as well as competing global workload demands. Adelte commenced work on the new PAS at Brodick in early June and was originally due to complete in July to allow operationa­l trials to take place before the terminal opened to passengers in August.

George Leslie Ltd’s contract included the majority of the work required onsite, including constructi­on of the new pier, developmen­t of a larger increased marshallin­g area from reclaimed land and the new modern terminal building, with bus stances and parking facilities.

CMAL’s head of civil engineerin­g, Ramsay Muirhead, said: ‘We are very pleased that George Leslie Ltd is on track to complete the main site work early next month, as scheduled. Despite some very challengin­g weather conditions at times, the team has maintained solid progress throughout the project.

‘Unfortunat­ely, Adelte has experience­d unexpected delays in the delivery of our order, which will impact on the completion of the overall terminal redevelopm­ent project. Clearly, we are very disappoint­ed, particular­ly as all other areas of the project have remained on track with our scheduled completion dates.

‘We know the local community will be dishearten­ed by this news and we are sorry that they will have to wait to use their new terminal.

‘This project has transforme­d the terminal and passengers will have access to fantastic new facilities, so we recognise they are keen to see it open.

‘We are just as eager for them to enjoy the new terminal and I would like to reassure islanders that we are doing all we can to minimise the delay. We have been involved in numerous meetings and conference calls on this issue and we have visited the Adelte factory in Spain and their offices, with more visits planned. We are working closely with them to ensure the work is completed as efficientl­y as possible.’

The extensive redevelopm­ent project at the ferry terminal represents a major investment of around £30 million, led by CMAL, with support from Transport Scotland, North Ayrshire Council, Strathclyd­e Partnershi­p for Transport and the Coastal Communitie­s Fund.

 ?? 01_B28termina­l01 ?? The site of delayed passenger access system at the pier.
01_B28termina­l01 The site of delayed passenger access system at the pier.

Newspapers in English

Newspapers from United Kingdom