The Arran Banner

Rock armour shipped in to save Pirnmill seawall

- By Hugh Boag editor@arranbanne­r.co.uk

Urgent works have started to save a severely storm damaged seawall which has led to part of the main road round Arran crumbling into the sea.

The rock revetment works to the south of Pirnmill require 2,000 tonnes of rock armour shipped in from the mainland to shore up the seawall. Preparator­y works started on Monday and the work is likely to last for four weeks. The project will cost £268, 800.

As a result of a heavy storm, large sections of the gabion basket seawall were swept into the sea or badly damaged leaving the main C147 road, on the west of the island, vulnerable to erosion by the sea in the future if left unattended. The Pirnmill Village Associatio­n has been pushing for this work to be carried out for some time.

A North Ayrshire Council spokeswoma­n said: ‘The coastal protection for the C147 road in this area currently consists of a length of masonry seawall, rock revetment and gabion basket seawall. The coastal protection works generally consist of the removal of the damaged gabion baskets and installing a further section of rock armour as an extension of the existing revetment. The project is being part-funded from the Crown Estate Net Revenue Allocation Scheme.’

The contractor for the project is W I & A Gilbert Ltd of Dalry, with John Thomson Constructi­on of Lamlash sub-contracted to bring the materials to the island. The rock is being delivered from Hillhouse quarry in Dundonald to Troon where it is being loaded on to a landing craft, the Red Princess, and brought to Arran. Two shipments have already been made with a third due early next week.

‘This was considered the most favourable and long-lasting solution, with the least disruption and impact on the community,’ the council spokeswoma­n added.

The alternativ­e would have been to use the main CalMac ferries for delivery of the rock supplies, which would have seriously affected island travel capacity, especially during Covid-19 restrictio­ns. The rock would then have had to be trucked over The String to Pirnmill.

The landing site at Rubha Airigh was first used during the constructi­on of the long sea outfall from the Isle of Arran Distillery at Lochranza four years ago and there have been claims that in the future

it could be used for timber extraction­s, as Red Princess is normally seen in Brodick transporti­ng timber to the mainland, but these have been denied.

The site of the rock armour works is situated off road, so site traffic management will be to a minimum. However, there will be an increase in constructi­on traffic for the duration of the works at certain times for the supply of materials. All foreshores will be returned to their natural conditions after the works, the council says.

 ??  ?? A truck loaded with rock armour drives off the Red Princess.
A truck loaded with rock armour drives off the Red Princess.
 ??  ??
 ??  ??
 ??  ?? Top left, a truck is loaded with stone from the Red Princess at the temporary landing site. 01_B32rock01; above right, a digger prepares to start work on the rock armour. 01_B32rock05; below, the storm erosion damage to the road is clear.
01_B32rock04; the badly eroded road south of Pirnmill with the new rock delivered seen on the shore. 01_B32rock03.
Top left, a truck is loaded with stone from the Red Princess at the temporary landing site. 01_B32rock01; above right, a digger prepares to start work on the rock armour. 01_B32rock05; below, the storm erosion damage to the road is clear. 01_B32rock04; the badly eroded road south of Pirnmill with the new rock delivered seen on the shore. 01_B32rock03.
 ??  ??
 ??  ??

Newspapers in English

Newspapers from United Kingdom