The Arran Banner

Work to start on Ardrossan harbour next year... maybe

- By Hugh Boag editor@arranbanne­r.co.uk

The long-awaited work to improve Ardrossan harbour should start next year with completion by 2023, the ministeria­l-led taskforce has said, but these dates may change.

The latest estimate for the cost of the works is £35m to £40m.

They will see the realignmen­t of the main Arran berth, a new linkspan, quay improvemen­ts and a new passenger access system to a new terminal building, among other works.

The latest details have emerged from a series of questions the Isle of Arran Ferry Committee first asked last January which have now been updated and posted on the Transport Scotland website.

The developmen­t works at Ardrossan are being overseen by the taskforce which brings together Transport Scotland, Peel Ports Group Ltd, North Ayrshire Council (NAC), CalMac Ferries Ltd (CFL), Caledonian Maritime Assets Ltd (CMAL), the Arran Ferry Committee and Kenneth Gibson MSP.

Infrastruc­ture works

In its statement to the ferry committee the taskforce says: ‘The project is currently in the planning and design phase. We are currently working towards the Arran berth infrastruc­ture works commencing in 2021; with completion of the works expected in 2023. However, these dates are subject to change taking account of tender/procuremen­t and contract award stages. A more detailed programme will be available once a contractor is appointed.’

It states that the Scottish government is committed to the delivery of the MV Glen Sannox to the Ardrossan to Brodick route, the subject of so many delays, which necessitat­es the proposed works to the Arran berth to ensure the vessel won’t overhang the berth as this results in poor mooring arrangemen­t and fender support. The taskforce has ruled out the MV Glen Sannox using the alternativ­e Irish berth as it is too big.

Confidence level

The ferry committee asked the taskforce: ‘What confidence level do you have that the Irish berth will cope during the works?’ It replied: ‘Peels Ports Group has confirmed that under normal weather conditions the Irish Berth can accommodat­e services to Brodick throughout the constructi­on period.

‘The linkspan works are now complete with the exception of the fall arrest system and the applicatio­n of the anti-slip treatment to the deck; these elements will be completed after the civil engineerin­g works to the Irish Berth.

‘The civil engineerin­g works to the cantilever­ed deck have been tendered and a contractor is to be appointed. Peel Ports Group is currently working towards these works being undertaken in spring 2021 and it will engage with CalMac regarding service continuity during the constructi­on.’

Then the ferry committee asked the million dollar question: ‘Are there contingenc­y plans for delays to work or if service needs to go to Troon for a period?’ The taskforce replied: ‘Yes, contingenc­y plans for disruption­s and any delays to the infrastruc­ture works are currently being developed as part of the service continuity planning.

‘Engagement with the communitie­s, including the Arran Ferry Committee, took place in January and February 2020 and more is expected throughout the year. The commitment from the taskforce is to retain services to Arran from the Irish berth throughout the closure period, subject to safe operating conditions and weather conditions at the port.

‘Contingenc­y planning is part of the continuity plan and as such Troon has been considered as an alternativ­e mainland berth, in the event the Irish Berth is unavailabl­e during the works. Throughout the period of the constructi­on works, Gourock may also be considered as an alternativ­e mainland berth.

‘No final decision has been taken in regard to the timetable during the works, including diversions to Troon as part of contingenc­y plans. CalMac will work closely with the community to understand service users’ needs and ensure these are considered within any temporary timetables. Engagement with the communitie­s will be undertaken on any proposals prior to a final plan being implemente­d.’

 ??  ?? The white triangle, circled, shows the area of Arran berth to be realigned.
The white triangle, circled, shows the area of Arran berth to be realigned.
 ??  ??

Newspapers in English

Newspapers from United Kingdom