Litany of failures leads to contractor’s removal from operation on major road in Perth after 14 weeks

- PETER JOHN MEIKLEM pmeiklem@thecourier.co.uk

A contractor for one of the UK’s biggest house builders has been banned from operating in Perth and Kinross after a litany of failures while working on a major road into the city centre.

Council bosses took action over the “totally unsatisfac­tory approach” of Persimmon Homes and its contractor­s Infinity Constructi­on.

Workers, who were installing two sets of traffic lights on Glasgow Road, packed up their tools on Wednesday.

The council intends to complete some of the outstandin­g work itself and then bill the company.

Commuters, residents and businesses have become increasing­ly dismayed by the levels of congestion since the work began in September.

Persimmon North Scotland’s managing director has been asked to explain the company’s failure “to meet a detailed list of issues”.

Infinity Constructi­on has been told it “shall receive no further consent to operate within the Perth and Kinross Council roads network”.

The council said no substitute contractor would be allowed back on site

We have asked the council to ensure that Persimmon have a proper plan to complete the works in the new year. COUNCILLOR WILLIE WILSON

until members were conditions would be met.

Businesses along the route said they were resigned to further delays and questioned why the council had asked for traffic lights be installed when granting planning permission to build around 100 properties close to the road.

A council spokespers­on said: “The council has, during the course of the contract, become increasing­ly concerned about the poor quality of the works and working practices on site, and the consequent overall impact on the local public roads network.

“Despite our repeated requests for action, provision of a detailed list of issues to be addressed, a one-week extension for completion of the works, and multiple assurances from the contractor and Persimmon Homes, the works are still incomplete and our concerns remain.”

Lib Dem councillor Willie Wilson said the project “has been nothing short of shambolic” from the very beginning.

“We have asked the council to ensure that Persimmon have a proper plan to complete the works in the new year. It is just not acceptable that Persimmon’s incompeten­ce of the last few months should be repeated,” he said.

A Persimmon Homes spokeswoma­n apologised for the inconvenie­nce. She said unforeseen ground conditions were to blame for the delay.

“Persimmon Homes is committed to completing the works to the satisfacti­on of the local authority and has requested an urgent strategy meeting to discuss and agree the process for the successful delivery of these outstandin­g works,” she added. satisfied all