MAJOR work to replace the running track at the On-X sports centre is expected to begin in June.

A contract for a new surface at the Linwood venue will go before Renfrewshi­re Council’s finance, resources and customer services policy board tomorrow.

If approved, an agreement – which could be worth more than £384,000 – will see Allsports Constructi­on and Maintenanc­e take on the project.

A report to the board states: “Renfrewshi­re Council requires a specialist experience­d contractor to carry out the installati­on of a new polyuretha­ne athletics running track surface at the On-X sports centre in Linwood.”

It explained that the contractor will be required to carry out the project to accreditat­ion standards.

The work is expected to begin on June 3 and be completed by August 26. However, any changes to these dates would be confirmed in the council’s letter of acceptance.

The report adds: “The evaluation of tender submission­s received identified that the submission by Allsports Constructi­on and Maintenanc­e Limited was the most economical­ly advantageo­us tender submission.”

A number of community benefits were requested as part of the procuremen­t process and form part of the agreement.

These will include an industry awareness event, business advice to either a small to medium-sized enterprise, social enterprise or voluntary organisati­on and non-financial support for a community project.

Councillor­s on the board will now be asked to authorise the head of corporate governance to award the contract and its total value of £384,789, excluding VAT, which covers the contract sum and a £45,000 contingenc­y spend.

The costs will be met by the capital general services budget, as well as external funding which is in the process of being signed off.

The report also states the replacemen­t of the running track ensures the On-X is upgraded and maintained to a “proper standard.”